Data Center M&A in 2026: What the Deals Say About Where Capacity Is Heading

The year’s biggest data center deals were priced on power. See who bought what and where capacity is heading next.

Ashish Gautam at Mordor Intelligence

Ashish Gautam

Updated November 17, 2026

Data center M&A in 2026: buyers paying for power and capacity worldwide

2026 Data Center Acquisitions Were Priced on Power

Data center M&A had a busy 2026. Aligned Data Centers sold for about USD 40 billion. Digital Realty paid USD 3.5 billion for Blackstone’s stake in three Northern Virginia data centers, a portfolio with a gross value of USD 7.8 billion. And Constellation Energy, a power company, spent USD 21.8 billion on Calpine’s power plants, then signed a 380 MW deal with CyrusOne for a data center beside one of them.

What ties these deals together is power. Digital Realty bought capacity that’s built, connected and leased for 15 years. The Aligned consortium bought a platform where much of the capacity is still planned, and committed another USD 5 billion to build it out. Constellation took the most direct route of all and bought the generation itself.

For anyone on either side of a deal, that difference matters a lot, and it’s hard to see from the outside. Announcements tend to roll running and planned capacity into one big number, and they rarely make clear who ends up controlling what. We built Mordor Intelligence’s Data Center Intelligence (DCI) platform to help with exactly this. It tracks projects by stage and links facilities to the companies that own and run them.

Below are the deals that shaped 2026, what they suggest about where capacity is heading, and what we’d check before the next one.

The Biggest Data Center Deals of 2026

Six deals tell most of the year’s story, from a USD 40 billion platform sale to five enterprise sites in Australia. Two of them are worth a closer look, because they show two very different ways of paying for power.

Selected Data Center M&A Deals, January to September 2026

Date (2026) Buyer Target Value (USD billion) What the buyer acquired Status
September 30 SoftBank Group DigitalBridge ~3.1 An asset manager investing in data centers, towers and fiber
Completed
September 2 CPP Investments (~51%), Equinix (~34%), Partners Group (~10%) atNorth 4.0 Eight Nordic data centers, plus four large sites in development
Completed
July 21 AIP, MGX and BlackRock’s Global Infrastructure Partners Aligned Data Centers ~40.0 (enterprise value) 51 campuses and 6.4+ GW of operational and planned capacity across the Americas
Completed (announced October 2025)
July 20 Next Capital Fujitsu’s Australian data center business Not disclosed Five enterprise data centers in Sydney, Melbourne, Brisbane and Perth
Agreed; completion expected later in 2026
June 29 Digital Realty Blackstone’s stakes in three Northern Virginia data centers 3.5 for Blackstone’s stake (portfolio gross value: 7.8) Blackstone’s 80% interest in two Manassas data centers and 50% interest in one Sterling data center, totaling 288 MW and fully leased to three hyperscale customers
Completed June 30, 2026
January 7 Constellation Energy Calpine ~21.8 A power generation fleet whose sites now host data center supply agreements
Completed

Source: Company announcements from SoftBank Group, atNorth, Aligned Data Centers, Macquarie Asset Management, Fujitsu and Digital Realty, and Constellation Energy’s Form 10-Q filed with the U.S. Securities and Exchange Commission, 2026

Why Power Now Drives Data Center M&A

Start with the wait. According to Lawrence Berkeley National Laboratory’s Queued Up: 2026 Edition, the median U.S. power plant that came online in 2025 spent 61 months between asking to connect to the grid and switching on. In 2008, it took 22 months. Data centers queue separately, but they plug into the same strained grid, so any megawatt that’s already connected carries a scarcity premium.

The two biggest deals show the two ways buyers paid for power. Digital Realty’s purchase covers three 96 MW buildings, each fully leased to an investment-grade hyperscale customer for 15 years, with 3.6% annual rent escalators and an expected stabilized capitalization rate of over 6.5%. The Aligned consortium bought an entire operating company whose 6.4+ GW mixes running and planned capacity, and committed USD 5 billion of growth capital to build out more of it. One buyer paid for certainty. The other paid for growth and took on the execution risk that comes with it.

So if you’re sizing up a target, the first thing worth knowing is how much of its pipeline is energized and how much is still planned. DCI’s project records follow each project from site identification to go-live using Mordor Intelligence’s own 19-phase research standard, so you can see that split project by project.

Constellation Energy went one step further and bought the source. It closed its USD 21.8 billion Calpine acquisition on January 7, 2026. Its latest Form 10-Q lists up to 1,160 MW of agreements with data center developer CyrusOne at two of those Texas gas plants, including 380 MW signed in the first quarter of 2026 at the Freestone Energy Center and an exclusive deal for a second 380 MW phase. A power company is now, in effect, a host for data centers. For the wider demand picture, see Mordor Intelligence’s United States Data Center Power Market report.

Weighing a single site rather than a whole portfolio? DCI’s Site Feasibility tool scores how close it sits to transmission lines, substations and generation, the same infrastructure these buyers paid for. It doesn’t assess available grid capacity or queue position, so confirming available power with the utility remains your next diligence step.

Where the Capacity Is Heading

Put the year’s deals on a map and two patterns show up. Capital is doubling down on hubs where power already flows, and it’s also heading for places where new power is easier to get.

  • Northern Virginia still commands the top price. Digital Realty called it the largest and most sought-after data center market, and paid USD 3.5 billion to increase its ownership of three fully leased buildings there. More in the Northern Virginia Data Center Market report.
  • The rest of the Americas’ big hubs, and Latin America. Aligned’s campuses sit in Chicago, Dallas, Ohio, Phoenix and Salt Lake City as well as Northern Virginia, and stretch to São Paulo, Querétaro and Santiago. See the South America Hyperscale Data Center Market report.
  • The Nordics, for clean power. atNorth runs eight data centers across all five Nordic countries and is building large sites in Kouvola, Ølgod, Sollefteå and Haugaland. CPP Investments named access to renewable power as part of the appeal. See the Nordic Data Center Market report.
  • Texas, right next to the power plant. Constellation’s CyrusOne deals put data center load beside gas-fired generation in Freestone and Bosque counties. When the grid is the bottleneck, sitting next to the supply is a strong hand to hold.
  • Australia, where enterprise capacity is changing hands. Fujitsu is selling five enterprise data centers in Sydney, Melbourne, Brisbane and Perth to Next Capital, and said Australian ownership is helpful given the customer base. See the Australia Data Center Market report.

A word of caution on all of this. Capital moves faster than concrete, and planned gigawatts often arrive late or not at all. Local politics can stall them too, through moratoria and planning pauses.

Who’s Buying, and How They’re Splitting the Bill

Almost nobody wrote a full check on their own in 2026. Look at how the money was put together:

  • The debt was bigger than the deal. atNorth’s USD 4 billion sale came with a USD 4.1 billion financing package from European and Canadian lenders, covering both the purchase and atNorth’s expansion. CPP Investments took about 51%, Equinix about 34% for USD 895 million, and Partners Group, the seller, bought back in for about 10%.
  • Stock instead of cash. Digital Realty paid Blackstone USD 3.5 billion for its stake, USD 2.3 billion of it in Digital Realty shares. Blackstone didn’t keep them for long: it sold the full block in a public offering that closed on July 1, 2026, the day after the deal completed.
  • Consortiums with very deep pockets. Aligned was the first investment for AIP, a partnership that aims to raise USD 30 billion of equity and up to USD 100 billion including debt. On top of the purchase price, the consortium committed USD 5 billion of growth capital.
  • Buying the investor. SoftBank Group bought DigitalBridge, an asset manager that invests in data centers, towers and fiber, for about USD 3.1 billion, and is keeping it as a separately run platform.
  • Corporates handing assets to specialists. Fujitsu is passing its Australian data centers to Next Capital, which is buying through its fifth fund.

All of which means the name on the building is often not the one in control. A single campus can sit under an operator, a joint venture and two or three funds. DCI’s operator profiles untangle that, mapping ownership, operations and linked facilities in one place.

What the 2026 Deals Mean for You

What you do with all this depends on your seat.

  • Investors and lenders. Ask for the pipeline split before you accept the headline gigawatts. Energized, under construction and planned capacity are three different assets, and only the first one is earning today.
  • Operators and developers. Financial buyers with fresh growth capital are now bidding for the same power and land you want. Watch where their money lands next, because that’s where competition for sites gets tighter.
  • Suppliers and contractors. Treat an ownership change as a sales trigger. New owners bring new budgets and new priorities, and the person who signs off may now sit at the sponsor rather than the operator.
  • Advisors and consultants. Clients will expect ownership maps and pipeline checks on a target within days. The firms that can show which projects are actually moving will win the work.

What We Expect in 2027

Our read on where data center M&A goes next, and what could change it:

  1. More power companies at the table. Constellation showed that owning generation lets you offer power, land and a grid connection as one package. We expect more utilities and independent power producers to buy, partner with or host data center developers.
  2. Tougher pricing on pipelines. As more planned capacity changes hands, buyers will price each project by its stage rather than paying for the portfolio headline. The gap between fully leased buildings and largely planned campuses gives them every reason to.
  3. More shared ownership. Minority stakes, consortiums and stock-funded deals will stay common, which means ownership maps go out of date faster.

The swing factor is the grid. If connection times start to shorten, the premium on energized megawatts shrinks and pipeline-heavy platforms start to look cheap. Lawrence Berkeley National Laboratory’s queue data shows no sign of that yet.

See What’s Inside the Next Deal Before It Closes

Every deal in this piece was public by the time you read about it. The edge goes to whoever understood the pipeline first.

Pick a target, a portfolio or a market you’re weighing. In a demo, we’ll walk through its operators, ownership and projects by stage together, so you know how much of the pipeline is real before anyone agrees on a price.

Book a demo →

About The Author
Ashish Gautam at Mordor Intelligence

Ashish Gautam

Associate Director, Technology, Media & Telecom Research

Ashish leads Technology, Media and Telecom (TMT) research at Mordor Intelligence, covering technology scouting, digital transformation and market-entry strategy. He helps clients make data-driven decisions across the TMT space.