Technology, Media and Telecom7 min read

Data Center Cancellations: How to Assess Which Projects Are at Risk

84% of cancelled data center capacity is in the US. Learn how to read the count and spot projects at risk.

Birendra Pandey at Mordor Intelligence

Birendra Pandey

Updated November 18, 2026

Data Center Cancellations: How to Spot Projects at Risk

Why the Cancellation Count Isn't the Number to Watch

In 2026, data center cancellations became a near-weekly headline, usually a county board denying a rezoning or a hyperscaler stepping back from a site. Mordor Intelligence's Data Center Intelligence (DCI) platform shows where they land. As per Mordor Intelligence estimates, DCI held 70 cancelled projects totaling 16.37 GW worldwide on November 10, 2026, from tracking that began in January 2023. Of those, 51 projects totaling 13.77 GW were in the United States, about 84% of all cancelled capacity.

That concentration is the first thing a global total hides. If you underwrite, advise on, or supply this market, the useful questions are which projects get cancelled, at what stage, and whether the ones in your model share their warning signs.

The cancellations sit against a large pipeline. On the same date, the global pipeline DCI tracks as planned, announced, or under construction stood at 735.73 gigawatts (GW). Only 246.49 GW of it, across 1,297 facilities, had work on site. Another 489.24 GW, across 1,991 facilities, was announced but not started.

A cancellation before construction removes capacity that was only ever a plan. One after work starts destroys committed capital, and a headline total counts both the same way. This guide shows how to assess which projects are at risk: what confirmed cancellations look like, how delays differ from cancellations, and the four warning signs to check.

Five Confirmed Cancellations and Where They Stopped

Each of these was confirmed by the developer's own withdrawal, recorded by the local government that handled it.

Five Confirmed Data Center Cancellations, 2024–2026

ProjectLocationDateLast stage (public record)ReasonSource
Amazon data center campuses at Calvert Cliffs (2.4 million square feet)Calvert County, MarylandAugust 2026Planning application filed with the countyWithdrawn after strong voter opposition to data centers in the county's June 2026 primaryCalvert County planning records; Maryland Matters, August 4, 2026
Tarboro DC, Energy Storage Solutions (300 MW, USD 19.2 billion)Edgecombe County, North CarolinaJuly 2026Special-use permit denied in late 2025Withdrawn after the permit denial, as the county weighed a 24-month moratoriumEdgecombe County Board of Commissioners, July 6, 2026
Holder Industrial Park expansion for data centers, Deltona CorporationCitrus County, FloridaJune 23, 2026Rezoning applicationsWithdrawn amid resident opposition, after the county adopted a one-year moratorium and refused to delay the hearingDeltona Corporation press release, June 23, 2026; Citrus County Board of County Commissioners
Mooresville Technology Park, Tract (USD 30 billion, about 400 acres)Mooresville, North CarolinaAugust 13, 2025Rezoning request, before the town board voteWithdrawn after resident opposition; the mayor said the town board would not approve itTown of Mooresville, August 13, 2025
West Valley data center campus, Tract (USD 14 billion, about 1,000 acres)Maricopa County, ArizonaMay 2024Rezoning and comprehensive plan amendment applicationsWithdrawn after the cities of Goodyear and Buckeye objected that it was incompatible with nearby residential land useMaricopa County Planning and Development Department

Source: county and town government records; company statements; Maryland Matters, 2026

All five ended before construction, at the application, rezoning, or permit stage, and in all five the developer withdrew. Four withdrew after organized resident opposition or objections from neighboring cities. The fifth withdrew after the county denied its special-use permit.

Five cases aren't a base rate; that's what DCI's 70 are for. But they show what the warning signs look like in practice. Every one had an application or a hearing on file, not an approval.

Cancelled, Delayed, or Paused: Why Every Count Is Different

Two sources can report very different cancellation counts for the same market and both be right, because they define a cancellation differently. One may count a proposal denied at a rezoning hearing before any formal announcement, another may add delayed or paused projects, and a third may report dollars of announced investment instead of projects or gigawatts.

DCI counts a project as cancelled only when its status changes to Cancelled. A project that's delayed or on hold stays in its current stage, visible as at risk rather than counted as dead. A project enters DCI at the strategy stage, as soon as its sponsor shares intent, so a proposal denied at rezoning or permitting is recorded too: it moves from Planned to Cancelled.

That makes DCI's count deliberately conservative, and it's built for base rates by market and operator. Before you compare any cancellation figure with another, check three things: what counts as cancelled, when a project enters the dataset, and whether the figure is in projects, gigawatts, or dollars.

Four Warning Signs a Project Is at Risk

Most cancellations look predictable in hindsight: the project showed at least one of these warning signs. When you're judging a single project rather than a pipeline total, check all four. A project that shows all four is a plan, whatever its press release says.

Four Warning Signs That a Project Is at Risk

SignalLower riskWarning sign
PowerA signed interconnection or power supply agreement, or on-site generation with its own permits
A utility load request, or a capacity figure in a press release
Land and permitsOwned land, approved rezoning, and issued air or environmental permits
A land option, a filed application, or a scheduled hearing
Sponsor and tenantA named operator that builds what it announces, or a signed anchor tenant
A newly formed developer, an unnamed client, or a codename with no operator
Capital and equipmentFinancing closed, a general contractor appointed, and long-lead electrical equipment ordered
A headline investment figure with no financing partner named

Source: Mordor Intelligence

All five cancellations above showed the land-and-permits warning sign. If you can check only one sign, though, check power. Grid access is the constraint a sponsor can't buy its way around quickly, and without it a project has no date it can commit to.

DCI covers two of the four signs today. The sponsor sign comes straight from the platform: each operator's record in DCI, read alongside the projects it has cancelled, tells you whether its announcements tend to become buildings. Power shows up at the country and region level in DCI Signals, so you can see where grid constraints are tightening before they surface in a single project's timeline. Facility-level power, financing, contractor, and equipment-order tracking is coming to DCI. Until then, permits and financing are checks you'll run project by project.

These signs raise or lower the risk; they don't settle the outcome. The Berkeley Lab data below shows that even signed grid agreements were withdrawn at scale. Use the four signs to rank projects against each other, then watch for risk tags in DCI Signals that suggest one is slipping.

Why Data Centers Get Cancelled

Every cancelled data center fails at least one of four things a project needs: power, permission, a sponsor that follows through, and capital. In 2026, permission was the most visible failure, but it's rarely the only one.

Rezoning hearings have become the most common place for a proposal to end, as four of the five cases above show. Residents push back on electricity prices, water use, noise, and land use, and county boards deny the request or the developer withdraws before the vote. States are moving too: in April 2026, Maine's legislature passed what would have been the first statewide moratorium on new data centers, and Governor Janet Mills vetoed it (Associated Press, 2026). Our read: opposition mostly ends proposals that haven't secured land, zoning, or permits, which is why opposition-driven cancellations tend to land before construction starts.

Grid access is the second filter, and regulators now apply it on purpose. Texas Senate Bill 6, signed in June 2025, requires large new loads to show site control, pay for interconnection studies, and disclose duplicate requests elsewhere in the state (Texas Legislature, 2025). Rules like these turn weak applications into cancellations earlier, which makes the pipeline easier to read. For the demand side, see Mordor Intelligence's United States Data Center Power Market report.

Permitting catches projects later. A site can have land and a utility letter and still stall on air permits for onsite generation, environmental reviews, or rights-of-way for the gas and transmission lines it depends on, and by then more money has been spent. On backup and onsite power, see the Data Center Generator Market report.

Sponsors change their plans too, including the largest buyers. In April 2025, Microsoft said it was halting early-stage data center projects in Licking County, Ohio, a USD 1 billion plan, and would keep two of the three sites as farmland (Associated Press, 2025). At the same time, Microsoft said it still planned to spend more than USD 80 billion on AI infrastructure in its fiscal year ending June 2025. Capital expenditure headlines and project pipelines can move in opposite directions.

An Announcement Is an Option, Not a Construction Schedule

Most announced capacity is a claim on land, power, or incentives. It becomes a building only if financing, grid access, permits, and a tenant all line up, and any one of them can fail.

The power sector shows what that looks like at scale. According to Lawrence Berkeley National Laboratory (U.S. Department of Energy, June 2026), only 13% of U.S. generation and storage capacity that requested grid interconnection from 2000 to 2020 was operating by the end of 2025. By then, 75% had withdrawn. Even a signed interconnection agreement wasn't safe: 41% of the capacity in agreements signed from 2000 to 2022 had withdrawn by the end of 2025.

Bar chart of U.S. grid interconnection outcomes at the end of 2025: 13% of capacity requested from 2000 to 2020 reached commercial operation and 75% withdrew, while 41% of capacity with interconnection agreements signed from 2000 to 2022 withdrew.

Outcomes of U.S. grid interconnection requests, status at end of 2025. Source: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, June 2026

Data centers aren't power plants, so don't apply a 13% conversion rate to them. But they share the same failure points: multi-year timelines, grid dependence, and financing that can disappear between announcement and groundbreaking. An announcement costs a sponsor little to make and little to withdraw, which makes it the easiest stage at which to cancel.

Data Center Cancellations Are Data, So DCI Keeps Them

DCI tracks every project through five stages: Planned, Announced, Under Construction, Commissioned, and Cancelled. A project can leave the pipeline in two ways, by reaching Commissioned or by being cancelled, and DCI records both.

Diagram of DCI project stages as of November 10, 2026: 698 planned facilities, 489.24 GW announced across 1,991 facilities, and 246.49 GW under construction across 1,297 facilities, in a 735.73 GW pipeline. Any stage can end in Cancelled, with 70 cancelled projects totaling 16.37 GW kept on record.

DCI project stages, global, as of November 10, 2026. Source: Mordor Intelligence

In a dataset that lists only active projects, a cancelled one simply disappears. The pipeline total shrinks, and nobody can see who over-committed or where. DCI keeps cancelled projects on record, which turns each failure into a data point you can use.

That record answers three questions a pipeline total can't:

  • What's the base rate? How often projects in a given market or size band end up cancelled. As per Mordor Intelligence estimates, DCI held 70 cancelled projects totaling 16.37 GW worldwide on November 10, 2026.
  • Whose announcements hold up? An operator that builds most of what it announces reads differently from one that builds a fraction of it. You can only see that ratio if the misses stay visible.
  • Where is it happening? Market by market, not as a global average. The US share of DCI's cancelled capacity, set out at the top of this article, is the clearest example.

The stage at which a project is cancelled tells you more than the count. A cancellation at Announced usually means a sponsor walked away from an option that cost little to hold. A cancellation during construction means capital was committed and lost, and it's a warning for every nearby project that shares the same grid, permits, or contractors. The second kind is far more expensive, and a headline tally counts it the same as the first. For the wider build picture, see the Data Center Construction Market report.

Status changes don't wait for a quarterly report. DCI Signals collects news on projects and operators, tags each item as an opportunity, risk, or neutral, and summarizes it. Ask DCI AI answers questions from DCI's internal datasets only, so its answers trace back to the same project records you see in the platform.

Want to see where cancellations sit in your market? We can pull them up with you in a short demo.

Schedule a demo →

What Stage-Level Data Changes for You

A cancellation headline means different things depending on the decision on your desk.

If you're deciding where to commit capital, which market to enter, or which partner to back, stage data separates supply you can count on from supply that's only been announced, and shows where cancellations are concentrating. When the decision is a valuation or a loan against a developer's pipeline, it shows the sponsor's mix by stage and the projects it has already walked away from. For a client deck or a diligence memo, it gives you a pipeline and cancellation figure split by stage, with a named source and a stated definition, so the number holds up when someone questions it. A supply forecast gets usable inputs, stage mix and cancellation rates, in place of one undifferentiated number. And a decision on how much manufacturing capacity to add can rest on projects under construction rather than on press releases.

In each case, the risk is the same: treating Announced capacity as if it were Under Construction. The cost shows up later as an overvalued asset, an idle production line, or a forecast that has to be withdrawn.

Five Questions to Ask of Any Pipeline or Cancellation Number

Before a pipeline or cancellation figure goes into a model, a memo, or a board deck, it should pass these five checks. They apply to DCI as much as to anyone else's number.

  1. Is it split by stage? A single total mixes intent with steel in the ground. If you can't see the split, you can't price the risk.
  2. What evidence moves a project between stages? A press release and a construction permit shouldn't carry the same weight. Ask for the definition of each stage.
  3. Are cancellations kept, and how are they defined? If cancelled projects drop out, you lose the base rate and the sponsor track record. If delays are counted as cancellations, the rate looks worse than it is.
  4. How current is it? A project's stage can change several times between quarterly reports. DCI refreshes daily and resets its baseline every quarter.
  5. How was the conversion rate built? The share of announced capacity that reaches construction is the number that turns a total into a forecast. It's also the easiest to get wrong, because a credible rate needs every stage change and every cancellation on file. If a dataset drops its misses, its conversion rate flatters the pipeline. Ask what's in the denominator before you use it.

Where Stage Data Stops

A stage gives you odds. A project under construction can still slip or stall, and the stage won't tell you when. DCI's forward projections, which run to 2033, are Mordor Intelligence estimates, so treat them as a view.

The same logic applies to talk of a data center bubble. Cancellations of early-stage proposals show a market filtering out weak projects. The warning signs are different: announced capacity growing while construction starts stay flat, or cancellations moving into projects already under construction. On November 10, 2026, announced capacity in DCI was roughly double the capacity under construction.

Stage data won't settle the outcome, but it stops you from reading a cancellation headline, or a 735.73 GW pipeline, as one number.

See Which Projects in Your Market Are at Risk

Pick the market you're underwriting, advising on, or selling into and book a demo. We'll show you which of its projects show warning signs, how much of its pipeline is past the Announced stage, and where its cancellations happened. DCI is built by the same research operation behind the rest of Mordor Intelligence: 550+ in-house analysts and around 500 expert interviews a month.

Book a demo →

About The Author
Birendra Pandey at Mordor Intelligence

Birendra Pandey

Advanced Product Group, Mordor Intelligence

Birendra Pandey leads Intelligence Platforms at Mordor Intelligence, building AI-first B2B data products. He has nearly two decades of experience scaling intelligence platforms across infrastructure, energy, real estate, and emerging technologies.

Related Reports