List of data centers in India by city, operator and project status
India runs 2,906.8 MW of data center IT load today and has more than ten times that, 30,680.8 MW, under construction or announced. This is no longer just a Mumbai story: Visakhapatnam, a city with almost no operating capacity, now holds a quarter of the national pipeline, and new campuses are being designed for 50–150 kW per rack, against 6 kW in a typical hall today.
Published November 25, 2026
- 524
- Projects tracked
- 2,906.8 MW
- Operating IT load
- 30,680.8 MW
- Pipeline IT load
- 112
- Operators
Mordor Intelligence, Data Center Intelligence research team. DCI India records, November 2026.
Key takeaways
- 01Mumbai still leads.The Mumbai Metropolitan Region (MMR) runs a third of India's operating capacity, 997.2 MW, and holds the largest pipeline, 7,719.5 MW.
- 02Vizag is the breakout.Visakhapatnam has 0.6 MW in operation but 7,582.7 MW under construction or announced, 25% of the national pipeline.
- 03New names are building the future.AirTrunk, Reliance Jio and RackBank lead the pipeline, while Sify, NTT DATA and STT GDC run the largest operating bases.
- 04Delivery is about to accelerate.1,296.8 MW is due in Q4 2026 and 3,233.2 MW in 2027, 3.4 and 8.4 times what India added in 2025.
How many data centers are there in India?
| Data Center Operator | Data Center Facility | City | Status | IT load capacity |
|---|---|---|---|---|
| STT GDC Pte Ltd | STT Ahmedabad DC 1 | Ahmedabad | Commissioned | 3 MW |
| CtrlS Data Centers Limited | Bangalore DC | Bengaluru | Commissioned | 12.5 MW |
| NTT DATA GROUP Corporation | Navi Mumbai Data Center (NAV1D) | Navi Mumbai | Under Construction | 40 MW |
| Status | Projects | IT load (MW) |
|---|---|---|
| Operating | 324 | 2,906.8 (current) |
| Under construction | 101 | 10,747.7 (expected) |
| Announced | 99 | 19,933.1 (expected) |
| Total | 524 | 33,587.6 |
Data centers in India by city
| City area | Projects | Operating | Under construction | Announced | Total |
|---|---|---|---|---|---|
| Mumbai Metropolitan Region | 124 | 997.2 | 2,175.4 | 5,544.1 | 8,716.7 |
| Visakhapatnam–Anakapalli | 24 | 0.6 | 2,323.8 | 5,258.9 | 7,583.3 |
| Hyderabad | 51 | 223.2 | 1,476.4 | 1,685 | 3,384.6 |
| Jamnagar | 2 | – | – | 3,133.3 | 3,133.3 |
| Delhi NCR | 79 | 366.4 | 1,194.7 | 1,261.0 | 2,822.1 |
| Raipur | 4 | 1.7 | 2,033.0 | – | 2,034.7 |
| Chennai | 51 | 520.4 | 554.2 | 300.2 | 1,374.8 |
| Pune | 32 | 210.1 | 517.4 | 226.2 | 953.7 |
| Bengaluru | 36 | 211.9 | 68.4 | 54.7 | 335.0 |
| Kolkata | 18 | 52.1 | 33.6 | 229.1 | 314.8 |
| Dholera | 1 | – | – | 198.4 | 198.4 |
| 58 other city areas | 102 | 323.2 | 370.8 | 2,042.2 | 2,736.2 |
| India | 524 | 2,906.8 | 10,747.7 | 19,933.1 | 33,587.6 |
The new hotspots: Visakhapatnam, Jamnagar and Raipur
Which operating data centers in India have the largest IT loads?
| Facility | Operator | City area | IT load (MW) | Rack density (kW) | Opened |
|---|---|---|---|---|---|
| HYD04 Building 1 | Microsoft | Hyderabad | 100.0 | 40 | 2024 |
| HYD 110 | Amazon Web Services | Hyderabad | 80.0 | 12 | 2022 |
| Sify Mumbai DC1 | Sify Technologies | MMR | 68.0 | 4 | 2014 |
| STT Chennai DC 2 | STT GDC | Chennai | 57.0 | 10 | 2010 |
| Sify Chennai 02 (Tower C) | Sify Technologies | Chennai | 52.0 | 6 | 2025 |
| Yotta NM1, Panvel | Yotta Data Services | MMR | 52.0 | 7 | 2020 |
| PDG MU1 (Buildings 1 and 2) | Princeton Digital Group | MMR | 48.0 | 10 | 2022 |
| MB3 Phase 1 | Equinix | MMR | 48.0 | 35 | 2026 |
| Chennai Data Center Park – DC1 | CtrlS Data Centers | Chennai | 45.0 | 8 | 2024 |
| Rabale Data Center (Tower 5) | Sify Technologies | MMR | 43.2 | 30 | 2025 |
Top data center operators in India
| Operator | Projects | Operating | Pipeline | Total |
|---|---|---|---|---|
| AirTrunk | 10 | 21.4 | 5,114.8 | 5,136.2 |
| Reliance Jio | 7 | 23.8 | 3,119.0 | 3,142.8 |
| RackBank Datacenters | 4 | 0 | 2,600.0 | 2,600.0 |
| CtrlS Data Centers | 39 | 234.9 | 2,201.1 | 2,436.0 |
| Sify Technologies | 23 | 361.3 | 1,241.3 | 1,602.6 |
| Fortune Hospitality & Infra | 4 | 0 | 1,600.0 | 1,600.0 |
| AdaniConneX | 15 | 55.8 | 1,512.7 | 1,568.5 |
| Reliance Industries | 4 | 0 | 1,363.5 | 1,363.5 |
| NTT DATA | 27 | 286.9 | 736.6 | 1,023.5 |
| Amazon Web Services | 6 | 97.2 | 713.9 | 811.1 |
Which operating data centers support at least 30 kW per rack?
| Facility | Operator | City area | IT load (MW) | Avg.Rack density (kW) | Opened |
|---|---|---|---|---|---|
| HYD04 Building 1 | Microsoft | Hyderabad | 100.0 | 40 | 2024 |
| MB3 Phase 1 | Equinix | MMR | 48.0 | 35 | 2026 |
| Rabale Data Center (Tower 5) | Sify Technologies | MMR | 43.2 | 30 | 2025 |
| Mumbai Tower 1 | CapitaLand | MMR | 34.0 | 30 | 2025 |
| Sify Noida 02 (Tower C) | Sify Technologies | Delhi NCR | 25.9 | 30 | 2025 |
| Kolkata (KOL 1) | Nxtra (Bharti Airtel) | Kolkata | 10.0 | 70 | 2025 |
| Silvernox Datacenter Mumbai DC | Silvernox | MMR | 2.5 | 60 | 2025 |
Upcoming data centers in India: the largest projects
Under construction
| Project | Operator | City area | IT load (MW) | Expected |
|---|---|---|---|---|
| Raipur (CEN1) | RackBank Datacenters | Raipur | 2,000.0 | 2026 |
| Bhogapuram East and West Expansion (Phase 2) | Reliance Industries | Visakhapatnam | 833.3 | 2030 |
| Hyderabad Phase 3 Data Center | AdaniConneX | Hyderabad | 595.2 | 2027 |
| Jewar Data Centre Phase 2 | AM Green | Delhi NCR | 513.3 | 2030 |
| Polipalli Village Campus (Phase 1) | Reliance Industries | Visakhapatnam | 396.8 | 2028 |
| GigaCampus ONE | RackBank Datacenters | Chennai | 360.0 | 2027 |
| Jewar Data Centre Phase 1 | AM Green | Delhi NCR | 304.8 | 2028 |
| BOM1 Data Center Phase 1 | Digital Edge | MMR | 300.0 | 2026 |
| Vizag Data Center | AdaniConneX | Visakhapatnam | 300.0 | 2029 |
| Rambilli Village DC3 | Visakhapatnam | 264.6 | 2028 |
Announced
| Project | Operator | City area | IT load (MW) | Expected | Avg.Rack density (kW) |
|---|---|---|---|---|---|
| Jamnagar DC | Reliance Jio | Jamnagar | 3,000.0 | 2030 | 150 |
| AirTrunk Raigad Data Center Campus | AirTrunk | MMR | 2,500.0 | 2030 | 75 |
| Vizag Data Center | AirTrunk | Visakhapatnam | 1,666.7 | 2030 | 75 |
| Anakapalli Data Center | ReNew AP Green Data Centre | Visakhapatnam | 813.0 | 2029 | 60 |
| OpenAI India DC1 | OpenAI | Delhi NCR | 500.0 | 2029 | 60 |
| Sify India DC1 | Sify Technologies | Visakhapatnam | 500.0 | 2028 | 50 |
| Green Integrated AI Data Center | AM AI Factory | Visakhapatnam | 416.3 | 2029 | 60 |
| Fortune Data Center Park – Module 1 | Fortune Hospitality & Infra | Hyderabad | 400.0 | 2028 | 50 |
| Fortune Data Center Park – Module 2 | Fortune Hospitality & Infra | Hyderabad | 400.0 | 2029 | 60 |
| Fortune Data Center Park – Module 3 | Fortune Hospitality & Infra | Hyderabad | 400.0 | 2030 | 75 |
When the new capacity arrives
| Year | Added by operating projects | Due from projects under construction | Due from announced projects |
|---|---|---|---|
| 2022 | 566.1 | – | – |
| 2023 | 275.1 | – | – |
| 2024 | 455.0 | – | – |
| 2025 | 386.0 | – | – |
| 2026 to date | 124.4 | – | – |
| Q4 2026 | – | 1,296.8 | – |
| 2027 | – | 3,233.2 | 2,206.9 |
| 2028 | – | 2,479.8 | 3,431.3 |
| 2029 | – | 1,297.6 | 3,161.4 |
| 2030 | – | 1,940.3 | 9,498.4 |
| 2031 | – | 500.0 | 805.1 |
| 2032–2036 | – | – | 830.0 |
Delivery will be staged rather than front-loaded. Projects under construction that are dated 2026 total 3,536.8 MW, but only 1,296.8 MW of that is expected to be live by year-end. RackBank's Raipur campus follows the pattern: it lists a 2026 date and an expected load of 2,000 MW, but only 20 MW is due in Q4 2026. Five projects lead the Q4 2026 delivery: Amazon Web Services' HYD 111 Phase 2, AdaniConneX's Navi Mumbai Data Center, Equinix's MB3 Phase 2, Digital Edge's BOM1 Phase 1 and Microsoft's HYD01.
From 2028, announced projects take over the calendar, peaking at 9,498.4 MW in 2030, the year Reliance Jio dates its Jamnagar campus and AirTrunk its Raigad and Vizag campuses. None of the announced projects has started construction yet, so this is the part of the pipeline with the most timing risk.
Three things to watch
- 01Q4 2026 and 2027 delivery.The first stages of the big campuses, and the 3,233.2 MW due in 2027, will show whether India's build is on schedule.
- 02Announcements turning into construction.Jamnagar, Raigad and Visakhapatnam hold the largest announced campuses; a construction start at any of them would reshape the national map.
- 03Contractors and cooling choices.65 large facilities have yet to name an EPC or general contractor, or disclose a cooling method, because they are still in planning and analysis. Once they have established a proper channel, they will have contractors and suppliers for cooling equipment. Thus, these disclosures will decide which suppliers win the work.
Questions about data centers in India
01
How many data centers are in India?
DCI tracks 543 data center project records in India: 524 active projects (324 operating, 101 under construction and 99 announced), plus 16 planned and 3 cancelled. Each building or construction phase is counted once.
02
Which Indian city has the most data center capacity?
The Mumbai Metropolitan Region leads, with 997.2 MW of operating IT load across 124 projects, ahead of Chennai with 520.4 MW. The MMR also leads the pipeline, with 7,719.5 MW under construction or announced.
03
Which Indian cities have the most data center projects?
The MMR has 124 projects, followed by Delhi-NCR (79), Hyderabad (51), Chennai (51), and Bengaluru (36). India's projects span 69 city areas.
04
Who is building India's new data centers?
AirTrunk leads the pipeline with 5,114.8 MW, followed by Reliance Jio with 3,119.0 MW and RackBank Datacenters with 2,600.0 MW. Google, Amazon Web Services and Microsoft are building their own capacity in Visakhapatnam, Mumbai and Hyderabad.
05
Which Indian data centers run at 30 kW per rack or more?
Seven operating facilities do: Microsoft's HYD04 Building 1, Equinix's MB3 Phase 1, Sify's Rabale Tower 5 and Noida 02 Tower C, CapitaLand's Mumbai Tower 1, Nxtra's Kolkata (KOL 1) and Silvernox's Mumbai DC. In the pipeline, 151 projects plan 30 kW per rack or more.
06
How much data center capacity is due in 2026 and 2027?
Projects under construction are expected to add 1,296.8 MW in Q4 2026 and 3,233.2 MW in 2027, on top of the 2,906.8 MW currently operating. If all dates hold, India will reach about 7,436.8 MW by the end of 2027.
07
Does Data Center Intelligence offer a free trial?
Yes. The DCI team starts with a 30-minute walkthrough tailored to your market, then opens a trial for your team.
Explore the Indian projects in DCI
For a new development, use the DCI site selection tool to compare candidate locations against your project requirements. DCI holds the full Indian list with filters for city area, operator, status, capacity band, rack density, and expected year. A demonstration walks through the facilities and projects that match your market or supplier brief.
Scheduling takes two minutes. No commitment.