Mordor Intelligence Logo
Login

List of data centers in India by city, operator and project status

India runs 2,906.8 MW of data center IT load today and has more than ten times that, 30,680.8 MW, under construction or announced. This is no longer just a Mumbai story: Visakhapatnam, a city with almost no operating capacity, now holds a quarter of the national pipeline, and new campuses are being designed for 50–150 kW per rack, against 6 kW in a typical hall today.

Published November 25, 2026

524
Projects tracked
2,906.8 MW
Operating IT load
30,680.8 MW
Pipeline IT load
112
Operators

Mordor Intelligence, Data Center Intelligence research team. DCI India records, November 2026.

Key takeaways

  • 01Mumbai still leads.
    The Mumbai Metropolitan Region (MMR) runs a third of India's operating capacity, 997.2 MW, and holds the largest pipeline, 7,719.5 MW.
  • 02Vizag is the breakout.
    Visakhapatnam has 0.6 MW in operation but 7,582.7 MW under construction or announced, 25% of the national pipeline.
  • 03New names are building the future.
    AirTrunk, Reliance Jio and RackBank lead the pipeline, while Sify, NTT DATA and STT GDC run the largest operating bases.
  • 04Delivery is about to accelerate.
    1,296.8 MW is due in Q4 2026 and 3,233.2 MW in 2027, 3.4 and 8.4 times what India added in 2025.

How many data centers are there in India?

Data Center Intelligence (DCI) tracks 524 data center project records in India. These include 324 operating, 101 under construction and 99 announced projects.
Selected data centers in India
Mordor Intelligence, Data Center Intelligence research team. DCI India records, November 2026.
Data Center OperatorData Center FacilityCityStatusIT load capacity
STT GDC Pte LtdSTT Ahmedabad DC 1AhmedabadCommissioned3 MW
CtrlS Data Centers LimitedBangalore DCBengaluruCommissioned12.5 MW
NTT DATA GROUP CorporationNavi Mumbai Data Center (NAV1D)Navi MumbaiUnder Construction40 MW
India data center projects by status
India data center projects and IT load by status, checked November 2026.
StatusProjectsIT load (MW)
Operating3242,906.8 (current)
Under construction10110,747.7 (expected)
Announced9919,933.1 (expected)
Total52433,587.6

Data centers in India by city

Four city areas account for 72.5% of India's operating capacity: the MMR (997.2 MW), Chennai (520.4 MW), Delhi NCR (366.4 MW) and Hyderabad (223.2 MW). Bengaluru (211.9 MW) and Pune (210.1 MW) follow closely behind.
India data center IT load by city area
City areas ranked by total operating and pipeline IT load (MW), checked November 2026.
City areaProjectsOperatingUnder constructionAnnouncedTotal
Mumbai Metropolitan Region124997.22,175.45,544.18,716.7
Visakhapatnam–Anakapalli240.62,323.85,258.97,583.3
Hyderabad51223.21,476.41,6853,384.6
Jamnagar2––3,133.33,133.3
Delhi NCR79366.41,194.71,261.02,822.1
Raipur41.72,033.0–2,034.7
Chennai51520.4554.2300.21,374.8
Pune32210.1517.4226.2953.7
Bengaluru36211.968.454.7335.0
Kolkata1852.133.6229.1314.8
Dholera1––198.4198.4
58 other city areas102323.2370.82,042.22,736.2
India5242,906.810,747.719,933.133,587.6

The new hotspots: Visakhapatnam, Jamnagar and Raipur

Visakhapatnam is the sharpest change on the map. Reliance Industries is building two campuses there: Bhogapuram (833.3 MW) and Polipalli (396.8 MW); Google is building three village sites, each at 264.6 MW; and AdaniConneX is building a 300 MW campus. AirTrunk's 1,666.7 MW Vizag Data Center leads the announcements.
Jamnagar holds 3,133.3 MW in the pipeline from a standing start, almost all of it Reliance Jio's announced 3,000 MW campus. Raipur has 2,033.0 MW under construction, compared with 1.7 MW in operation, led by RackBank's 2,000 MW CEN1 campus. Closer to Delhi, AM Green's two Jewar phases add 818.1 MW under construction.
The MMR itself is spreading beyond the city. AirTrunk has announced a 2,500 MW campus at Pen in Raigad and ReNew has announced four 187.5 MW sites at Panvel, Khalapur, Taloja and Bhokharpada.

Which operating data centers in India have the largest IT loads?

The ten largest operating data centers, ranked by IT load.
The ten largest operating Indian data centers by IT load, checked November 2026.
FacilityOperatorCity areaIT load (MW)Rack density (kW)Opened
HYD04 Building 1MicrosoftHyderabad100.0402024
HYD 110Amazon Web ServicesHyderabad80.0122022
Sify Mumbai DC1Sify TechnologiesMMR68.042014
STT Chennai DC 2STT GDCChennai57.0102010
Sify Chennai 02 (Tower C)Sify TechnologiesChennai52.062025
Yotta NM1, PanvelYotta Data ServicesMMR52.072020
PDG MU1 (Buildings 1 and 2)Princeton Digital GroupMMR48.0102022
MB3 Phase 1EquinixMMR48.0352026
Chennai Data Center Park – DC1CtrlS Data CentersChennai45.082024
Rabale Data Center (Tower 5)Sify TechnologiesMMR43.2302025

Top data center operators in India

India's operators split cleanly into two groups. Builders lead the pipeline: AirTrunk, including the sites it took over from Lumina CloudInfra, has 5,136.2 MW across 10 projects, ahead of Reliance Jio at 3,142.8 MW and RackBank Datacenters at 2,600.0 MW. Incumbents run today's market: Sify has the largest operating base at 361.3 MW, followed by NTT DATA (286.9 MW), STT GDC (265.8 MW), CtrlS (234.9 MW) and Nxtra (228.5 MW).
Leading data center operators in India
The ten largest operators by total operating and pipeline IT load (MW).
The ten largest Indian data center operators by total operating and pipeline IT load, checked November 2026.
OperatorProjectsOperatingPipelineTotal
AirTrunk1021.45,114.85,136.2
Reliance Jio723.83,119.03,142.8
RackBank Datacenters402,600.02,600.0
CtrlS Data Centers39234.92,201.12,436.0
Sify Technologies23361.31,241.31,602.6
Fortune Hospitality & Infra401,600.01,600.0
AdaniConneX1555.81,512.71,568.5
Reliance Industries401,363.51,363.5
NTT DATA27286.9736.61,023.5
Amazon Web Services697.2713.9811.1

Which operating data centers support at least 30 kW per rack?

Rack density shows India's move toward AI workloads more clearly than any other measure. The median operating facility runs at 6 kW per rack. Projects under construction have a median of 70 kW, and announced projects have a median of 60 kW. In all, 151 of the 200 projects under construction or announced plan 30 kW per rack or more, and they carry 89% of pipeline IT load.
High-density capacity in operation is still rare. None of the 249 facilities opened before 2023 reach 30 kW per rack. These seven, all opened since 2024, do:
India operating data centers at 30 kW per rack or more
Operating data centers at 30 kW per rack or more.
Operating Indian data centers at 30 kW per rack or more, checked November 2026.
FacilityOperatorCity areaIT load (MW)Avg.Rack density (kW)Opened
HYD04 Building 1MicrosoftHyderabad100.0402024
MB3 Phase 1EquinixMMR48.0352026
Rabale Data Center (Tower 5)Sify TechnologiesMMR43.2302025
Mumbai Tower 1CapitaLandMMR34.0302025
Sify Noida 02 (Tower C)Sify TechnologiesDelhi NCR25.9302025
Kolkata (KOL 1)Nxtra (Bharti Airtel)Kolkata10.0702025
Silvernox Datacenter Mumbai DCSilvernoxMMR2.5602025

Upcoming data centers in India: the largest projects

Under construction

DCI tracks 66 Indian phases of 20 MW or more under construction, with 10,449.6 MW of expected IT load, or 97% of everything being built. Twenty of them, worth 3,435.5 MW, are dated 2026; 30 are dated 2027, and 16 are dated 2028 or later.
Largest Indian data center projects under construction
The ten largest projects under construction.
The ten largest Indian data center projects under construction, checked November 2026.
ProjectOperatorCity areaIT load (MW)Expected
Raipur (CEN1)RackBank DatacentersRaipur2,000.02026
Bhogapuram East and West Expansion (Phase 2)Reliance IndustriesVisakhapatnam833.32030
Hyderabad Phase 3 Data CenterAdaniConneXHyderabad595.22027
Jewar Data Centre Phase 2AM GreenDelhi NCR513.32030
Polipalli Village Campus (Phase 1)Reliance IndustriesVisakhapatnam396.82028
GigaCampus ONERackBank DatacentersChennai360.02027
Jewar Data Centre Phase 1AM GreenDelhi NCR304.82028
BOM1 Data Center Phase 1Digital EdgeMMR300.02026
Vizag Data CenterAdaniConneXVisakhapatnam300.02029
Rambilli Village DC3GoogleVisakhapatnam264.62028

Announced

Announced projects add 19,933.1 MW across 99 projects, and all ten of the largest plan 50 kW per rack or more. Reliance Jio's Jamnagar campus alone accounts for 3,000.0 MW, 15% of the total, and plans 150 kW per rack.
Largest Indian data center projects announced
The ten largest announced projects.
The ten largest announced Indian data center projects, checked November 2026.
ProjectOperatorCity areaIT load (MW)ExpectedAvg.Rack density (kW)
Jamnagar DCReliance JioJamnagar3,000.02030150
AirTrunk Raigad Data Center CampusAirTrunkMMR2,500.0203075
Vizag Data CenterAirTrunkVisakhapatnam1,666.7203075
Anakapalli Data CenterReNew AP Green Data CentreVisakhapatnam813.0202960
OpenAI India DC1OpenAIDelhi NCR500.0202960
Sify India DC1Sify TechnologiesVisakhapatnam500.0202850
Green Integrated AI Data CenterAM AI FactoryVisakhapatnam416.3202960
Fortune Data Center Park – Module 1Fortune Hospitality & InfraHyderabad400.0202850
Fortune Data Center Park – Module 2Fortune Hospitality & InfraHyderabad400.0202960
Fortune Data Center Park – Module 3Fortune Hospitality & InfraHyderabad400.0203075

When the new capacity arrives

India added 455.0 MW of operating capacity in 2024 and 386.0 MW in 2025. Projects under construction are due to add 1,296.8 MW in Q4 2026 and 3,233.2 MW in 2027. If every date holds, India's operating IT load reaches about 7,436.8 MW by the end of 2027, more than double today's.
India IT load added or due by year
IT load added or due by year (MW).
India IT load added or due by year, 2022–2036 (MW), checked November 2026.
YearAdded by operating projectsDue from projects under constructionDue from announced projects
2022566.1––
2023275.1––
2024455.0––
2025386.0––
2026 to date124.4––
Q4 2026–1,296.8–
2027–3,233.22,206.9
2028–2,479.83,431.3
2029–1,297.63,161.4
2030–1,940.39,498.4
2031–500.0805.1
2032–2036––830.0

Delivery will be staged rather than front-loaded. Projects under construction that are dated 2026 total 3,536.8 MW, but only 1,296.8 MW of that is expected to be live by year-end. RackBank's Raipur campus follows the pattern: it lists a 2026 date and an expected load of 2,000 MW, but only 20 MW is due in Q4 2026. Five projects lead the Q4 2026 delivery: Amazon Web Services' HYD 111 Phase 2, AdaniConneX's Navi Mumbai Data Center, Equinix's MB3 Phase 2, Digital Edge's BOM1 Phase 1 and Microsoft's HYD01.

From 2028, announced projects take over the calendar, peaking at 9,498.4 MW in 2030, the year Reliance Jio dates its Jamnagar campus and AirTrunk its Raigad and Vizag campuses. None of the announced projects has started construction yet, so this is the part of the pipeline with the most timing risk.

Three things to watch

  • 01Q4 2026 and 2027 delivery.
    The first stages of the big campuses, and the 3,233.2 MW due in 2027, will show whether India's build is on schedule.
  • 02Announcements turning into construction.
    Jamnagar, Raigad and Visakhapatnam hold the largest announced campuses; a construction start at any of them would reshape the national map.
  • 03Contractors and cooling choices.
    65 large facilities have yet to name an EPC or general contractor, or disclose a cooling method, because they are still in planning and analysis. Once they have established a proper channel, they will have contractors and suppliers for cooling equipment. Thus, these disclosures will decide which suppliers win the work.

Questions about data centers in India

  • 01

    How many data centers are in India?

    DCI tracks 543 data center project records in India: 524 active projects (324 operating, 101 under construction and 99 announced), plus 16 planned and 3 cancelled. Each building or construction phase is counted once.

  • 02

    Which Indian city has the most data center capacity?

    The Mumbai Metropolitan Region leads, with 997.2 MW of operating IT load across 124 projects, ahead of Chennai with 520.4 MW. The MMR also leads the pipeline, with 7,719.5 MW under construction or announced.

  • 03

    Which Indian cities have the most data center projects?

    The MMR has 124 projects, followed by Delhi-NCR (79), Hyderabad (51), Chennai (51), and Bengaluru (36). India's projects span 69 city areas.

  • 04

    Who is building India's new data centers?

    AirTrunk leads the pipeline with 5,114.8 MW, followed by Reliance Jio with 3,119.0 MW and RackBank Datacenters with 2,600.0 MW. Google, Amazon Web Services and Microsoft are building their own capacity in Visakhapatnam, Mumbai and Hyderabad.

  • 05

    Which Indian data centers run at 30 kW per rack or more?

    Seven operating facilities do: Microsoft's HYD04 Building 1, Equinix's MB3 Phase 1, Sify's Rabale Tower 5 and Noida 02 Tower C, CapitaLand's Mumbai Tower 1, Nxtra's Kolkata (KOL 1) and Silvernox's Mumbai DC. In the pipeline, 151 projects plan 30 kW per rack or more.

  • 06

    How much data center capacity is due in 2026 and 2027?

    Projects under construction are expected to add 1,296.8 MW in Q4 2026 and 3,233.2 MW in 2027, on top of the 2,906.8 MW currently operating. If all dates hold, India will reach about 7,436.8 MW by the end of 2027.

  • 07

    Does Data Center Intelligence offer a free trial?

    Yes. The DCI team starts with a 30-minute walkthrough tailored to your market, then opens a trial for your team.

Explore the Indian projects in DCI

For a new development, use the DCI site selection tool to compare candidate locations against your project requirements. DCI holds the full Indian list with filters for city area, operator, status, capacity band, rack density, and expected year. A demonstration walks through the facilities and projects that match your market or supplier brief.

Scheduling takes two minutes. No commitment.