Data centers in Chennai by location, operator and project status
Chennai is India's second-largest data center market, and two corridors run most of it. Siruseri, on OMR, overtook Ambattur in 2025 and now runs 185.3 MW against 166.4 MW. But Ambattur is building again, and the biggest projects in Chennai's 1,374.8 MW pipeline are going up outside both.
Published November 25, 2026
- 520.4 MW
- Chennai, operating
- 1,374.8 MW
- Chennai, pipeline
- 166.4 MW
- Ambattur, operating
- 185.3 MW
- Siruseri, operating
Facility data as of 25 October 2026
Key takeaways
- Two corridors, two-thirds of the city.Ambattur and Siruseri together run 351.7 MW, 67.6% of Chennai's operating IT load.
- Siruseri leads today.A record 2025, with 98.2 MW brought online, took Siruseri past Ambattur, which added nothing that year.
- Ambattur leads tomorrow.Ambattur accounts for 139.6 MW of the two corridors' 155.6 MW pipeline, reaching 306.0 MW by 2028 if every phase arrives on time.
- The big money is elsewhere.The two corridors hold only 11% of Chennai's pipeline. RackBank's 360 MW campus in Sriperumbudur alone is more than twice their combined pipeline.
| Facility | Operator | City | Status | IT load |
|---|---|---|---|---|
| STT Chennai DC 1 | STT GDC Pte Ltd | VSB, Chennai | Commissioned | 3.6 MW |
| Chennai Data Center Park- DC 2 | CtrlS Data Centers Limited | 20, 3rd Main Rd, Ambattur Industrial Estate, Chennai, Tamil Nadu 600058, India | Commissioned | 27 MW |
| STT Chennai 4 | STT GDC Pte Ltd | Chennai, Tamil Nadu, India | Under Construction | 18 MW |
Where are the data centers in Chennai?
Chennai holds 18% of India's operating data center IT load, second only to the Mumbai Metropolitan Region. Data Center Intelligence (DCI) tracks 51 projects from 31 operators in the city: 33 operating with 520.4 MW, 11 under construction with 634.5 MW, and 7 announced with 740.3 MW. The pipeline is 2.6 times the size of today's operating base.
Most of today's capacity sits in two places: Ambattur Industrial Estate along MTH Road in the north-west, and SIPCOT IT Park in Siruseri, off OMR on the city's southern IT corridor. They grew up for different reasons and serve different needs, which is why buyers so often compare them.
Directory sites report different totals for Chennai because some count campuses and others count individual buildings. DCI counts each building or construction phase only once; accordingly, Chennai's 51 projects span 39 campuses.
For how Chennai compares with Mumbai, Hyderabad and India’s other hubs, see our India data center records page.
Map of Chennai's data center localities
Map: total tracked IT load by locality (operating, under construction and announced). Circles mark locality centers, not building positions.
How do Ambattur and Siruseri compare?
| Ambattur | Siruseri | |
|---|---|---|
| Location | Ambattur Industrial Estate, MTH Road | SIPCOT IT Park, Siruseri (OMR) |
| Operating IT load | 166.4 MW | 185.3 MW |
| Operating buildings | 5 | 8 |
| Operators | 4 | 6 |
| Typical operating building (median) | 27.0 MW | 21.2 MW |
| Largest building | STT Chennai DC 2, 57.0 MW | Sify Chennai 02 Tower C, 52.0 MW |
| Largest campus | CtrlS Chennai Data Center Park, 72.0 MW (43% of the area) | Sify Chennai 02, 103.1 MW (55.6% of the area) |
| Under construction | 3 phases, 59.6 MW | 1 phase, 16.0 MW |
| Announced | 1 building, 80.0 MW | None |
Ambattur is the corridor of big halls. Its median operating building is 27.0 MW, and 4 operators run it, including STT GDC's 57.0 MW Chennai DC 2, which has been running since 2010, and CtrlS's two-building Chennai Data Center Park.
Siruseri is the corridor of choice. It has more buildings and more operators, and more of its capacity is new: three of its eight operating buildings opened in 2025. Sify's three-tower Chennai 02 campus anchors it, with Techno Digital, AdaniConneX, STT GDC, Equinix and Nxtra alongside.
Data centers in Ambattur and Siruseri
Every tracked building and phase in the two corridors.
| Corridor | Facility | Operator | Status | IT load (MW) | Year |
|---|---|---|---|---|---|
| Ambattur | STT Chennai DC 2 | STT GDC | Operating | 57.0 | 2010 |
| Ambattur | Chennai Data Center Park, DC1 | CtrlS | Operating | 45.0 | 2024 |
| Ambattur | Chennai Data Center Park, DC2 | CtrlS | Operating | 27.0 | 2024 |
| Ambattur | MAA10 Building 1 | Digital Connexion | Operating | 20.0 | 2024 |
| Ambattur | NTT Chennai 2A | NTT DATA | Operating | 17.4 | 2023 |
| Ambattur | Iron Mountain CHN-1 | Iron Mountain | Under construction | 23.2 | Q4 2026 |
| Ambattur | NTT Chennai 2, Building B | NTT DATA | Under construction | 17.4 | Q4 2026 |
| Ambattur | Iron Mountain CHN-2 | Iron Mountain | Under construction | 19.0 | 2028 |
| Ambattur | MAA10 Building 2 | Digital Connexion | Announced | 80.0 | 2028 |
| Siruseri | Sify Chennai 02, Tower C | Sify | Operating | 52.0 | 2025 |
| Siruseri | Techno Digital Chennai Data Center | Techno Digital | Operating | 36.0 | 2025 |
| Siruseri | Sify Chennai 02, Tower B | Sify | Operating | 25.7 | 2023 |
| Siruseri | Sify Chennai 02, Tower A | Sify | Operating | 25.4 | 2024 |
| Siruseri | AdaniConneX Chennai 1, Phase 1 | AdaniConneX | Operating | 17.0 | 2022 |
| Siruseri | STT Chennai DC 3 | STT GDC | Operating | 15.0 | 2021 |
| Siruseri | Equinix CN1 | Equinix | Operating | 10.2 | 2025 |
| Siruseri | Nxtra Siruseri 1 (CHE 2) | Nxtra by Airtel | Operating | 4.0 | 2018 |
| Siruseri | AdaniConneX Chennai 1, Phase 2 | AdaniConneX | Under construction | 16.0 | Q4 2026 |
How Siruseri took the lead
For most of the past decade, Ambattur was the bigger corridor, largely on the strength of STT's Chennai DC 2. Ambattur remained ahead in 2023 when Sify opened Tower B, and extended its lead in 2024 as CtrlS opened two buildings and Digital Connexion opened MAA10, adding 92.0 MW in a single year.
Then came Siruseri's breakout year. In 2025, Sify's 52.0 MW Tower C, Techno Digital's 36.0 MW building and Equinix's CN1 came online, adding 98.2 MW. Ambattur added nothing, and Siruseri finished the year 18.9 MW ahead.
| Year-end | Ambattur | Siruseri | Leader |
|---|---|---|---|
| 2021 | 57.0 | 19.0 | Ambattur |
| 2022 | 57.0 | 36.0 | Ambattur |
| 2023 | 74.4 | 61.7 | Ambattur |
| 2024 | 166.4 | 87.1 | Ambattur |
| 2025 | 166.4 | 185.3 | Siruseri |
| 2026, if on schedule | 207.0 | 201.3 | Ambattur |
| 2028, if on schedule | 306.0 | 201.3 | Ambattur |
Data center projects planned in Ambattur and Siruseri
The pipeline points the other way. Ambattur has three phases under construction, and one announced building, together worth 139.6 MW. Siruseri has a single 16.0 MW phase under construction and nothing announced, so, based on current plans, its growth stops at 201.3 MW.
| Project | Corridor | Status | IT load (MW) | Target | Rack design (kW) |
|---|---|---|---|---|---|
| MAA10 Building 2 (Digital Connexion) | Ambattur | Announced | 80.0 | 2028 | — |
| Iron Mountain CHN-1 | Ambattur | Under construction | 23.2 | Q4 2026 | 12 |
| Iron Mountain CHN-2 | Ambattur | Under construction | 19.0 | 2028 | 13 |
| NTT Chennai 2, Building B | Ambattur | Under construction | 17.4 | Q4 2026 | 70 |
| AdaniConneX Chennai 1, Phase 2 | Siruseri | Under construction | 16.0 | Q4 2026 | 70 |
The end of 2026 is close. If all three Q4 2026 phases open on time, Siruseri ends the year at 201.3 MW and Ambattur at 207.0 MW, with Ambattur ahead by 5.7 MW.
By 2028, Ambattur is ahead. Iron Mountain's CHN-2 and Digital Connexion's 80.0 MW MAA10 Building 2 would take Ambattur to 306.0 MW. MAA10 Building 2 has no construction start yet, so it is the biggest swing factor; even without it, Ambattur reaches 226.0 MW and still leads.
AI density is arriving. NTT's Building B and AdaniConneX's Phase 2 are both designed for 70 kW per rack, against 12–13 kW at Iron Mountain's phases. Neither operator has disclosed a cooling method, but densities at that level usually call for liquid cooling.
For suppliers: the projects worth watching
Iron Mountain's CHN-1 is the only phase in either corridor that is under construction and larger than 20 MW. It is due in Q4 2026, so its main packages are, in MI's view, likely to have already been awarded, leaving commissioning, spares and service. Iron Mountain's CHN-2, due in 2028 and just under 20 MW, is earlier in its build and the more likely source of new equipment orders. No EPC, MEP or cooling contractor has yet been publicly named for any of these phases, so each operator's project team remains the first point of contact.
Beyond the two corridors: where Chennai's biggest projects are
Outside Ambattur and Siruseri, Chennai runs 168.7 MW today, with 558.9 MW under construction and 660.3 MW announced. That pipeline is almost eight times that of the two established corridors, and it is led by much larger campuses on the city's outskirts.
| Project | Operator | Status | IT load (MW) |
|---|---|---|---|
| GigaCampus ONE | RackBank Datacenters | Under construction | 360.0 |
| Chennai DC1 | AirTrunk | Announced | 216.0 |
| Chennai site | HyperVault | Announced | 120.0 |
| Chennai Data Center | Colt | Under construction | 73.9 |
| Chennai campus | L&T/Vyoma | Pipeline | 41.2 |
| STT Chennai 4 | STT GDC | Under construction | 18.0 |
These projects shift the center of gravity. RackBank's GigaCampus ONE, due in 2027, is larger on its own than the whole of Siruseri today, and AirTrunk's announced Chennai DC1 is bigger than any building in either corridor.
Which Chennai locations fit the buyer's needs?
- Need space now?
Siruseri offers more operators and the newest halls, with three buildings opened in 2025.
- Planning for 2027–2028?
Ambattur is where the corridor capacity is being added, with Iron Mountain and Digital Connexion leading.
- Need high density?
Watch NTT's Building B and AdaniConneX's Phase 2, both designed for 70 kW per rack and due in Q4 2026.
- Need hyperscale?
Look beyond both corridors, to Sriperumbudur and the large announced campuses around the city.
Questions about data centers in Chennai
01
How many data centers are in Chennai?
DCI tracks 51 data center projects in Chennai from 31 operators: 33 operating, 11 under construction, and 7 announced. Together they hold 520.4 MW of operating IT load and 1,374.8 MW in the pipeline.
02
Which is bigger, Ambattur or Siruseri?
Siruseri runs more today, with 185.3 MW of operating IT load against 166.4 MW in Ambattur. Ambattur has the larger pipeline, 139.6 MW against 16.0 MW, and would overtake Siruseri by the end of 2026 if its projects open on schedule.
03
Which data centers are in Siruseri?
Siruseri's operating data centers include Sify's Chennai 02 campus (Towers A, B and C), Techno Digital's Chennai Data Center, AdaniConneX Chennai 1, STT Chennai DC 3, Equinix CN1 and Nxtra's Siruseri 1.
04
Which data centers are in Ambattur?
Ambattur's operating data centers are STT Chennai DC 2, CtrlS's Chennai Data Center Park (DC1 and DC2), Digital Connexion's MAA10 Building 1, and NTT's Chennai 2A. Iron Mountain and NTT are building new phases there.
05
What data center projects are under construction in Chennai?
In the two corridors: Iron Mountain CHN-1 and CHN-2 and NTT Chennai 2 Building B in Ambattur, and AdaniConneX Chennai 1 Phase 2 in Siruseri. Elsewhere, RackBank's 360 MW GigaCampus ONE in Sriperumbudur, Colt's Chennai Data Center, and STT Chennai 4 are under construction.
06
Does Data Center Intelligence offer a free trial?
Yes. The DCI team starts with a 30-minute walkthrough tailored to your market, then opens a trial for your team.
Explore the Chennai projects in Data Center Intelligence
Data Center Intelligence holds the full Chennai list, with filters for locality, campus, operator, status, capacity band, and target date. A demonstration walks through the facilities and phases that match your market or supplier brief.
Scheduling takes two minutes. No commitment.