How are Data Center Locations Chosen? A Site Selection Guide

Decided on Evidence: How Mordor Intelligence's Data Center Intelligence (DCI) Platform Finds the Right Site.

Published November 16, 2026

945 TWh
Global data center electricity demand by 2030
$10.7M/MW
Build cost in 2025, up from $7.7M in 2020
4+ years
Grid-connection waits in primary markets

1. Why site feasibility has become the decision that matters most

The UK data center industry presents a significant opportunity, but identifying the right location is critical to securing capacity and avoiding costly grid-connection delays. For a buyer seeking 50 MW at one of three UK sites, Crabtree Hill scored highest under the buyer's initial requirements and was the first choice for further checks. For this example, we used the DCI site selection tool to compare locations against their project requirements.
The urgency is reinforced by the scale of the industry's expansion. Global data center electricity demand is projected to more than double to 945 TWh by 2030, while approximately 97 GW of new capacity is expected to be added between 2025 and 2030. However, with grid-connection waits exceeding four years in primary markets and construction costs rising from $7.7 million/MW in 2020 to $10.7 million/MW in 2025, site selection has become a critical investment decision.
For a deeper understanding of global capacity expansion and market forecasts, refer to our Data Center Market Report.
DCI's research team puts it this way: developers used to bring power to the site, and now they have to bring the site to the power. Site feasibility is no longer a box to tick before design starts. It is the strategic decision that shapes everything that follows.

2. Data center site selection: seven factors DCI checks

DCI assesses each site across seven dimensions and about 40 metrics. DCI benchmarks each metric, rates it, and links it to a named, mapped asset. The table below matches each dimension to what industry research says matters and to what DCI measures.
DCI's seven assessment dimensions, why each matters for site selection, and the parameters DCI evaluates for each.
DCI dimensionWhy this matters for site selectionParameters DCI evaluates
1. Power & GridPower is the deciding factor: industry experts call solving for power the number one priority for site selection. Survey respondents expect median campuses to reach 250–300 MW by 2030.Available capacity (MW); number of grid connection points; substation voltage class; distance to transmission lines
2. Energy Generation EcosystemRenewables and gas will lead new supply. Operators are moving beyond PPAs to behind-the-meter power and battery storage. Renewables over private wire can cut power costs by 40%.PPA, open-access and utility supply potential; generation-mix diversity; renewable zones; future generation pipeline (GW); distance to gas, nuclear, solar, wind, hydro and coal assets
3. ConnectivityLatency and proximity to customers rank third among site-selection criteria. Better subsea connectivity is opening new markets to developers.Fiber operators; cloud on-ramps; IXPs; metro fiber density; PoP distance; subsea cable landing stations
4. Risk & ResilienceOne in ten outages still causes serious disruption. Climate limits how efficiently operators can cool a site.Cyclone/wind risk; distance to hazardous industry; wildfire/heat risk; flight paths; oil and gas infrastructure
5. Land & BuildabilityGigawatt-scale development needs land, power and water together. Community support ranks second only to speed to power.Residential proximity; protected areas; commercial land price (by quartile); water bodies; elevation/slope
6. Market & CompetitionTight vacancy and preleasing into 2027 and beyond reward sites near established demand, while power shortages push operators to new locations at the edge of major hubs.Nearby facilities and MW; announced projects; operator density; vacancy
7. Logistics & AccessRemote mega-sites face labour, housing and equipment-delivery problems, which is pushing developers towards prefabrication.Construction supply chain; equipment import routes; highway, airport, port and rail proximity

Three inferences that shape how DCI scores

  • 01Scores reflect decision impact
    DCI tags each dimension Critical, High or Medium. Power and Connectivity are Critical, which matches the industry consensus that these are hardest to fix later.
  • 02Teams can trace every finding
    DCI names the substation, the IXP and the rail station, with distances in kilometres. Teams can check any score, which investors and lenders increasingly expect.
  • 03The output is a decision
    Each dimension carries a Go, Conditional Go, Watchlist / Hold or No-Go signal, along with the conditions needed to move a site from Conditional to Go.
How DCI scores access to fiber network operators

Connectivity accounts for 20% of the total site feasibility score and evaluates the availability, diversity, density and accessibility of digital infrastructure required to support data center operations.

The score is determined by the number of independent fiber network operators available to serve the proposed data center location.

DCI's fiber-operator scoring scale, from zero operators to five or more, and its weight within the Connectivity dimension.
Number of Fiber OperatorsScore (out of 100)Weight Contribution (25%)
5 or More10025%
48020%
36015%
24010%
1205%
000%

Calculation Example: If four fiber operators are available, the score is 80/100, contributing 20 points out of the 25 allocated to Fiber Operators within the Connectivity assessment.

Disqualification condition: If the site fails a mandatory minimum connectivity requirement, such as the availability of a viable fiber connection or required physical route diversity, it may be disqualified regardless of its overall feasibility score.

3. How three UK sites compare for a 50 MW requirement

To see how the framework behaves in practice, we put three UK sites through DCI under one buyer brief: CAPACITY Default (10 MW – 50 MW), DEVELOPMENT PREFERENCE Industry Baseline. All three sit in the same country, power market and regulatory regime, so the differences come from the sites themselves. The sites are a London-edge location at Crabtree Hill in Epping Forest, a site at Winkfield inside the established Bracknell and West London cluster, and a regional site outside Sheffield with no local data center market.

What the buyer requires

R1: no Critical-impact group may carry the Decision Signal No-Go.
R2: the Available Capacity proxy must be at least 50 MW, the top of the brief.
R3: among the sites that pass, prefer the highest Overall Feasibility score.

How each site scored and why Crabtree Hill ranked first

Crabtree Hill, Epping Forest
Winkfield
Sheffield
Actual DCI results (score / Decision Signal, with key measured evidence) for Crabtree Hill, Winkfield and Sheffield across all seven assessment groups.
Assessment group (Impact)Crabtree Hill, Epping Forest, EnglandWinkfield, EnglandSheffield, England
Power & Grid (Critical)98 / Conditional Go: 275 kV substation 2.77 km; transmission 2.73 km; 3,778 MW (Expected- Not Confirmed)83 / Watchlist / Hold: 33 kV substation 2.01 km; transmission 16.25 km; 1,213 MW (Expected- Not Confirmed)92 / Conditional Go: 66 kV substation 5.55 km; transmission 5.68 km; 1,027 MW (Expected- Not Confirmed) about 36.8 km away
Energy Generation Ecosystem (High)75 / Conditional Go: 2 generation types; solar 7.21 km; gas 12.41 km80 / Conditional Go: 3 generation types; solar 13.90 km; hydro 15.20 km; gas 20.83 km84 / Go: 4 generation types; solar 13.37 km; hydro 19.86 km; gas 20.10 km
Connectivity (Critical)49 / Watchlist / Hold: no local fiber operator; sparse metro fiber; IXP 13.85 km; PoP 16.06 km49 / Watchlist / Hold: no local fiber operator; sparse metro fiber; IXP 5.46 km; PoP 17.96 km68 / Conditional Go: 3 fiber operators, nearest 23.14 km; medium metro fiber; IXP 20.28 km; PoP 33.49 km
Risk & Resilience (High)58 / Conditional Go: wind High; industrial site 11.56 km; aerodrome 2.83 km55 / Conditional Go: wind High; industrial site 6.85 km; secondary flight corridor55 / Conditional Go: wind High; industrial site 7.84 km; secondary flight corridor
Land & Buildability (Medium; High at Sheffield)93 / Go: flat; minimal residential and protected-area conflict; USD 650/sqm85 / Go: slope 3.96%; minimal residential conflict; USD 820/sqm, highest quartile94 / Go: slope 4.32%; minimal residential conflict; USD 185/sqm
Market & Competition (High)89 / Go: 12 DCs, 121.90 MW; 13 announced, 902.56 MW; 16 operators95 / Go: 64 DCs, 723.55 MW; 11 announced, 2,210.22 MW; 41 operators8 / Watchlist / Hold: no nearby facilities, announced projects or operators
Logistics & Access (Medium)74 / Conditional Go: airport 2.83 km; rail 12.53 km75 / Go: rail 2.21 km; airport 11.39 km73 / Go: rail 5.28 km; airport 41.12 km
Overall Feasibility78.45 / Conditional Go. VERDICT: CONDITIONAL72.85 / Watchlist / Hold. VERDICT: CONDITIONAL72.1 / Conditional Go. VERDICT: CONDITIONAL
R1 / R2Pass / PassPass / PassPass / Pass

Preferred site: Crabtree Hill, by 5.6 points over Winkfield. All three sites pass R1 and R2, so the base brief alone does not separate them on risk. Crabtree Hill leads because it is the only site with a substation that DCI rates as a suitable voltage class: 275 kV at 2.77 km. It still carries Watchlist / Hold on Connectivity, so its lead depends on securing carrier fiber.

How a change in one requirement changes the preferred site

A headline score hides which constraint binds. We tested three single changes to the brief, one at a time: a substation voltage minimum, a rail-access distance, and requiring both Critical groups at Conditional Go or better.
  • Original buyer rulesHighest qualifying scoreCrabtree Hill
  • Substation voltageAt least 132 kVCrabtree Hill
  • Rail accessWithin 10 kmWinkfield
  • Power and connectivityBoth Conditional Go or betterSheffield
How a single added buyer requirement changes the preferred site among Crabtree Hill, Winkfield and Sheffield.
Requirement addedCrabtree HillWinkfieldSheffieldPreferred siteWhy, in measured results
Substation Voltage Class of at least 132 kV (DCI target 132–220 kV)Pass: 275 kV at 2.77 km, rated suitableFail: 33 kV at 2.01 kmFail: 66 kV at 5.55 kmCrabtree Hill (unchanged, now the only site that qualifies)Both alternatives need a voltage upgrade before they can serve the brief
Rail Access within 10 kmFail: 12.53 kmPass: 2.21 kmPass: 5.28 kmChanges to WinkfieldCrabtree Hill's rail station sits 2.53 km beyond the benchmark. Winkfield leads Sheffield by 0.75 points but carries Watchlist / Hold on Power & Grid, so the switch depends on a high-voltage connection route
Every Critical group at Conditional Go or betterFail: Connectivity at Watchlist / HoldFail: Power & Grid and Connectivity at Watchlist / HoldPass: both Critical groups at Conditional GoChanges to SheffieldThe lowest-scoring site becomes the only one that qualifies. The buyer then has to accept a market with no local data centers and secure an anchor customer

The combinations tell the same story. If the voltage and rail requirements apply together, no site qualifies and the shortlist has to widen. Voltage plus the Critical-group rule also leaves no site, while rail plus the Critical-group rule leaves Sheffield. Three sites in one country, assessed under one brief, produce three different preferred sites as soon as a buyer states what actually matters for the project.

What the buyer must confirm before choosing a site

Main missing evidence and the next check for each of the three sites.
SiteMain missing evidenceNext check
Crabtree HillFirm utility capacity and a delivery date behind the 3,778 MW proxy; local fiber, with no operator identified; aviation clearance next to Stapleford Aerodrome; a confirmed highway connectionQueue position and energisation date at Warley 275 kV; carrier builds to the London East IXPs about 14–17 km away; aviation safeguarding and an Epping Forest planning review
WinkfieldA high-voltage connection route, with 33 kV nearest and transmission 16.25 km away; local fiber; land cost in the highest quartileUtility study for a high-voltage connection and its timeline; diverse carrier routes to the Bracknell IXPs; an all-in land and planning cost before land control
SheffieldA deliverable connection, with 66 kV nearest and the capacity proxy about 36.8 km away; local data center demand; a nearby PoP, now 33.49 km awayInterconnection study with upgrade scope, cost and date; an anchor customer before land control; committed carrier builds and wind design criteria

The comparison turns a shortlist into a sequence of decisions: where to commit, where to spend diligence money, and where to stop early. Stopping early is often the most valuable outcome of all.

4. Conclusion and key takeaways

The AI build-out has made location the scarcest input in the data center business. Capital, demand and technology are all available; energised, connected and buildable land is not. The three sites above show what good feasibility work does in that environment. It shows that the highest score and the right choice are not always the same site. It identifies the single constraint that holds each site back, whether that is voltage, fiber or demand. And it gives every shortlisted site a concrete list of what has to be true before it reaches Go.
  • 01Power decides first.
    Grid waits of four years or more and an expected doubling of capacity by 2030 make speed to power the gating test for every site.
  • 02A single score is not a decision.
    Sheffield has the lowest Overall Feasibility score of the three, yet it is the only site whose Critical groups all carry Conditional Go. The binding constraint matters more than the headline number.
  • 03Strengths do not cancel a failed gate.
    A deep market cannot rescue a site with a 33 kV connection and no local fiber operator, and cheap land cannot replace local demand.
  • 04The buyer's rules can change the answer.
    A voltage requirement confirms Crabtree Hill, a rail requirement switches the choice to Winkfield and a Critical-group requirement switches it to Sheffield. State the rules before you rank.
  • 05Conditional is a starting point.
    All three sites return a Conditional verdict. The most useful output is the specific set of conditions that would move each site to Go, so that diligence spend follows the evidence.

5. One platform for every stakeholder: how each one evaluates data center site feasibility

Every stakeholder in a data center project looks at the same site through a different lens. The table below summarises what each one evaluates and where DCI answers that question.
What each data center stakeholder evaluates, and how DCI answers that question.
StakeholderWhat they evaluateHow DCI answers it
Developers and hyperscalersSpeed to power comes first, followed by community support, latency and proximity to customers. 84% of decision-makers rank power access in their top three.Power & Grid measures available capacity, substation voltage class, connection points and transmission distance. Land & Buildability and Connectivity cover community conflict and latency.
Investors and lendersThey ask what could strand the asset. 39% of global investors cite regulation and power availability as their biggest challenge.Impact-tagged scores and a Decision Signal for each dimension expose any failed gate before capital moves. The missing-evidence list shows where diligence money should go.
OperatorsThey need to run the site efficiently and staff it. Nearly two-thirds of operators struggle to hire or keep staff, and climate limits cooling efficiency.Risk & Resilience flags heat, wildfire and hazard exposure. Logistics & Access measures highway, rail and airport proximity for staff and equipment movement.
Utilities and energy plannersThey test whether the grid can carry the load. Developers report a one-to-two-year gap between expected and actual power delivery.Power & Grid maps connection points, voltage and transmission. Energy Generation Ecosystem tracks the generation mix, renewable zones and the future generation pipeline.
Tenants and enterprisesThey want capacity when they need it. Global vacancy sits at 6.6%, and preleasing stretches into 2027 and beyond.Market & Competition counts nearby facilities and MW, announced projects, operator density and vacancy. Connectivity maps fiber operators, cloud on-ramps and IXPs.
Governments and regulatorsThey weigh what the community gains or loses. Amsterdam restricts new facilities of 70 MW or more.Land & Buildability measures residential proximity, protected areas and water bodies. Risk & Resilience flags hazardous industry and flight paths.
See how different teams use DCI. Each stakeholder asks a different question, yet every question maps to one or more DCI dimensions. A site that satisfies one stakeholder but fails another is not feasible, so teams need one evidence base that answers all of them at once.
DCI gives every stakeholder that evidence base on one platform. Developers test speed to power, investors see which gate could strand the asset, operators check access and climate risk, utilities see the grid position, tenants see the market, and regulators see the land-use footprint. All of them work from the same seven dimensions, about 40 benchmarked metrics, named assets and measured distances, applied consistently to every site on a shortlist in any geography. That makes DCI a one-stop solution for the key data center stakeholders, from first screen to investment decision.
Have a shortlist to test, or a site you are unsure about? Talk to Mordor Intelligence's Datacenter Intelligence team at info@mordorintelligence.com.