Data center feasibility study for three UK sites
Three UK sites, one buyer brief, seven DCI dimensions: how Crabtree Hill, Winkfield and Sheffield compare, which site earns the next round of site due diligence, and what could change that answer.
Published November 17, 2026
- 78.45
- Crabtree Hill — Overall Feasibility
- 72.85
- Winkfield — Overall Feasibility
- 72.1
- Sheffield — Overall Feasibility
1. What does a data center feasibility study check?
A shortlist of three sites usually arrives with three different stories: one sits next to a major market, one has a large power figure attached to it, and one has cheaper, easier land. A buyer cannot fund full site due diligence on all three at once, so the first real decision is which site earns that money. This worked case study makes that decision for three UK sites, using only the evidence in their Mordor Intelligence Datacenter Intelligence (DCI) Site Feasibility Reports, and shows where the answer holds, where it depends on the buyer's own rules, and where the evidence runs out.
The short answer: Crabtree Hill should move first, because it is the only site with a high-voltage substation that DCI rates as suitable. Crabtree Hill leads under the original rules, but the buyer still needs to confirm diverse fibre routes. If both power and connectivity must reach Conditional Go or better, Sheffield leads.
A data center feasibility study answers one question for several audiences: can this site be built, energised, connected and operated for the intended load, and what has to be true first? Developers and hyperscalers use it to rank land. Lenders and investors use it to see what could stall a new project before capital commits to land. Site selectors, operators and economic development teams use it to compare locations on the same evidence.
In practice, the word feasibility covers several distinct studies, each with a different owner and output. Confusing them is a common reason projects stall late. The table below separates the studies that apply to a new, greenfield site and shows where this worked case study fits. Acquisitions and existing operating facilities are outside the scope of this article.
| Study layer | Question it answers | Typical users | Covered in this article? |
|---|---|---|---|
| Site screening and technical feasibility | Which site is technically suitable for the brief, and what blocks it? | Developers, site selectors, investors | Yes: seven DCI dimensions across three sites |
| Power and utility engineering study | What capacity can the utility deliver, by when, through which route and upgrades? | Developers, utilities, lenders | Partly: proxies, voltage and distances only; dates and costs not available |
| Environmental, planning and permitting review | What consents, impact assessments and permits does the project need? | Developers, planning authorities | Partly: protected areas, residential proximity and hazards only |
| Financial feasibility and valuation | Do revenue, costs and financing support the project and its debt? | Lenders, investors, sponsors | No: requires an independent financial assessment |
This article is a completed technical feasibility decision, not a service outline. It uses measured evidence for three named sites, makes a recommendation and shows the evidence that would change it.
2. The buyer requirement: one brief, three UK sites
All three reports assess their site against the same brief. The DCI Site Feasibility tool takes two brief parameters, capacity band and development preference, and both are identical across the three reports. That shared brief is what makes the comparison fair: differences in score come from the sites, not from the requirement.
| Brief parameter | Documented value | Status |
|---|---|---|
| Capacity | Default (10 MW – 50 MW) | Identical in all three reports |
| Development preference | Industry Baseline | Identical in all three reports |
The three candidates span the London edge, the Bracknell and West London corridor, and South Yorkshire. Each report returns the same headline verdict, CONDITIONAL, which is exactly why a worked decision is needed: the verdict alone does not rank them.
| Site | Location data in report | Overall Feasibility | Report summary (directional) |
|---|---|---|---|
| Crabtree Hill, Epping Forest, England | City field: South Ockendon; coordinates 51.627663, 0.148470 | 78.45/100, Conditional Go (High) | Commercially promising London-edge site; progress only after securing a deliverable grid connection and multi-route carrier fiber. |
| Winkfield, England | City field: Winkfield; coordinates 51.370848, -0.718811 | 72.85/100, Watchlist / Hold (Critical) | Exceptional market adjacency, but not development-ready; current evidence supports a strategic reserve site rather than immediate land commitment. |
| Sheffield, England | City field: Sheffield; coordinates 53.497321, -1.686925 | 72.1/100, Conditional Go (High) | Credible regional or edge candidate; not presently de-risked for hyperscale development. |
How to read the DCI results
DCI scores each of seven dimensions out of 100, assigns a Green, Amber or Red status, gives a Decision Signal (Go, Conditional Go, Watchlist / Hold or No-Go) and tags the dimension's Impact as Critical, High or Medium. Power & Grid and Connectivity carry Critical impact at all three sites.
Weightages. DCI combines the seven dimension scores into the Overall Feasibility score through a weighted scoring system, so the overall score is not a simple average. The simple averages are 76.57 for Crabtree Hill, 74.57 for Winkfield and 67.71 for Sheffield, against published overall scores of 78.45, 72.85 and 72.1. The Impact tags show relative importance at each site: Land & Buildability carries Medium impact at Crabtree Hill and Winkfield but High impact at Sheffield. The example below shows how the weighting works inside one dimension.
Example weightage system: Connectivity. Connectivity accounts for 20% of the total site feasibility score and evaluates the availability, diversity, density and accessibility of digital infrastructure required to support data center operations.
Fiber Operators: scoring methodology. The score is determined by the number of independent fiber network operators available to serve the proposed data center location.
| Number of fiber operators | Score (out of 100) | Weight contribution (25%) |
|---|---|---|
| 5 or more | 100 | 25% |
| 4 | 80 | 20% |
| 3 | 60 | 15% |
| 2 | 40 | 10% |
| 1 | 20 | 5% |
| 0 | 0 | 0% |
Calculation example: if four fiber operators are available, the score is 80/100, contributing 20 points out of the 25 allocated to Fiber Operators within the Connectivity assessment.
Applied to the three sites, Sheffield's 3 fiber operators score 60/100 and contribute 15 of the 25 points, while Crabtree Hill and Winkfield, with 0 operators each, score 0 on this sub-factor. This is one reason Sheffield leads Connectivity at 68 against 49 for the other two sites.
3. How the three sites compare on seven factors
Consolidated comparison
Format: score out of 100 · Status · Decision Signal · Impact. No dimension at any site carries a No-Go signal.
| DCI dimension | Crabtree Hill | Winkfield | Sheffield |
|---|---|---|---|
| 1. Power & Grid | 98 · Conditional Go · Critical | 83 · Watchlist / Hold · Critical | 92 · Conditional Go · Critical |
| 2. Energy Generation Ecosystem | 75 · Conditional Go · High | 80 · Conditional Go · High | 84 · Go · High |
| 3. Connectivity | 49 · Watchlist / Hold · Critical | 49 · Watchlist / Hold · Critical | 68 · Conditional Go · Critical |
| 4. Risk & Resilience | 58 · Conditional Go · High | 55 · Conditional Go · High | 55 · Conditional Go · High |
| 5. Land & Buildability | 93 · Go · Medium | 85 · Go · Medium | 94 · Go · High |
| 6. Market & Competition | 89 · Go · High | 95 · Go · High | 8 · Watchlist / Hold · High |
| 7. Logistics & Access | 74 · Conditional Go · Medium | 75 · Go · Medium | 73 · Go · Medium |
| Overall Feasibility | 78.45 · Conditional Go · High | 72.85 · Watchlist / Hold · Critical | 72.1 · Conditional Go · High |
Crabtree Hill: the strongest power case, held back by fiber
Strongest dimensions: Power & Grid (98) and Land & Buildability (93). The report records a 3,778.35 MW capacity proxy against a 75+ MW benchmark, Warley Substation at 275 kV at 13.414 km rated a suitable voltage class, 78 grid connection points, flat terrain below 2% slope, and minimal residential and protected-area constraint.
Weakest dimensions: Connectivity (49) and Risk & Resilience (58). The report identifies 0 fiber operators against a benchmark of 5 or more and classifies metro fiber density as Sparse. Wind risk is High, and the Flight Paths metric is rated Red with no value recorded, which requires further validation alongside Stapleford Aerodrome at 2.825 km.
Technical advantages: London cloud on-ramps (7 providers at 17.983 km), 66 IXPs with the nearest at 13.847 km and a PoP at 16.056 km give a credible metro-extension route. The market shows 12 nearby facilities with 121.90 MW, 13 announced projects with 902.56 MW and 16 operators.
Constraints: the transmission reference sits at 2.73 km against a sub-2 km benchmark, rail sits at 12.525 km against a sub-10 km benchmark, and Highway Access reads Unavailable. Commercial land price is 650 USD/sqm, third quartile.
Mandatory requirements not met or unverified: Connectivity, a Critical dimension, sits at Watchlist / Hold. Firm capacity, queue position and delivery date are unverified; the report itself states they must be secured.
Suitability: the strongest documented power foundation of the three for a 10–50 MW development, but not deployable until diverse carrier fiber is in place.
Winkfield has the strongest local market and needs a power connection check
Strongest dimensions: Market & Competition (95) and Land & Buildability (85). The report records 64 nearby facilities with 723.55 MW, 11 announced projects with 2,210.22 MW and 41 operators, plus minimal residential and protected-area constraint.
Weakest dimensions: Connectivity (49) and Risk & Resilience (55). The site shows 0 fiber operators, Sparse metro fiber and the nearest PoP (Equinix LD4, Slough) at 17.96 km, although 71 IXPs exist with the nearest at 5.459 km.
Technical advantages: Bagshot Rail Station at 2.214 km, Fairoaks Airport at 11.388 km, excellent construction supply-chain access, 107 grid connection points and a renewable-zone position.
Constraints: the nearest substation, Bagshot, is 33 kV at 2.01 km, rated Amber with a voltage upgrade required; the transmission reference, West Weybridge, sits at 16.25 km and is rated Red. Hazardous industry sits at 6.849 km, the site lies in a secondary flight corridor, slope is gentle at 2–5%, and land price is 820 USD/sqm, the highest quartile.
Mandatory requirements not met or unverified: both Critical dimensions, Power & Grid and Connectivity, sit at Watchlist / Hold, and the Overall Decision Signal is Watchlist / Hold. The report states that the 1,213.09 MW capacity proxy does not demonstrate an achievable site interconnection.
Suitability: the best market position of the three, but the report itself frames Winkfield as a strategic reserve site until a high-voltage connection route and diverse fiber are proven.
Sheffield: clears both Critical gates, but with no market evidence
Strongest dimensions: Land & Buildability (94) and Power & Grid (92). The report records minimal residential and protected-area constraint, 125 grid connection points and a 1,026.95 MW capacity proxy.
Weakest dimensions: Market & Competition (8) and Risk & Resilience (55). The report identifies 0 nearby facilities, no announced projects and 0 operators; it reads this as possible whitespace rather than proven demand.
Technical advantages: Connectivity scores 68, the highest of the three, with 3 fiber operators (nearest Abzorb at 23.142 km), Medium metro fiber density and 30 IXPs with the nearest at 20.281 km. Energy Generation Ecosystem earns a Go at 84 with 4 generation types. Penistone Rail Station sits at 5.276 km, and land price is 185 USD/sqm, second quartile.
Constraints: the nearest substation, Stocksbridge, is 66 kV at 5.55 km, below the 132–220 kV benchmark, and the transmission reference sits at 5.68 km. The report states that the capacity proxy sits about 36.8 km away and cannot be treated as deliverable site capacity. The nearest PoP sits at 33.485 km and Leeds Bradford Airport at 41.115 km.
Mandatory requirements not met or unverified: both Critical dimensions reach Conditional Go, but a high-voltage interconnection, upgrade scope and delivery date remain unverified, and Market & Competition sits at Watchlist / Hold.
Suitability: a credible regional or edge candidate with an anchor customer; the report does not support speculative hyperscale capacity here.
Power and connectivity evidence side by side
The two Critical dimensions decide this shortlist, so the measured evidence behind them deserves a direct comparison.
| Metric (benchmark) | Crabtree Hill | Winkfield | Sheffield |
|---|---|---|---|
| Available Capacity proxy (75+ MW) | 3,778.35 MW | 1,213.09 MW | 1,026.95 MW; about 36.8 km away |
| Substation voltage class (132–220 kV) | Warley 275 kV at 13.414 km | Bagshot 33 kV at 2.01 km | Stocksbridge 66 kV at 5.55 km |
| Transmission line proximity (nearest power line tower) (<2 km) | Brimsdown at 2.73 km | West Weybridge at 16.25 km | Stocksbridge at 5.68 km |
| Grid connection points (≥4) | 78 | 107 | 125 |
| Fiber operators (≥5) | 0 | 0 | 3 |
| Metro fiber density (Exceptional) | Sparse | Sparse | Medium |
| Nearest PoP (<2 km) | 16.056 km | 17.96 km | 33.485 km |
| Nearest IXP (≥4 IXPs) | 13.847 km; 66 IXPs | 5.459 km; 71 IXPs | 20.281 km; 30 IXPs |
The pattern is clear. Crabtree Hill leads on power quality, Sheffield leads on fiber depth, and Winkfield leads on neither Critical dimension despite the strongest market. Every capacity figure is a proxy; none of the reports confirms deliverable site capacity.
4. Which site should the buyer check first?
- 01Step 1, the No-Go screenA site with a No-Go in any Critical dimension drops out. No site fails this screen.
- 02Step 2, the power gatePower is the hardest constraint to fix, so the substation voltage class and transmission distance rank first.
- 03Step 3, the connectivity gateA Watchlist / Hold on Connectivity becomes the first condition the preferred site must clear.
- 04Step 4, the score as tie-breaker onlyThe Overall Feasibility score separates sites that are otherwise equivalent; it never overrides a failed gate.
| Decision test | Crabtree Hill | Winkfield | Sheffield |
|---|---|---|---|
| No-Go in any dimension | None | None | None |
| Power & Grid Decision Signal | Conditional Go | Watchlist / Hold | Conditional Go |
| High-voltage substation rated suitable | Yes: 275 kV, Green | No: 33 kV, upgrade required | No: 66 kV, upgrade needed |
| Connectivity Decision Signal | Watchlist / Hold | Watchlist / Hold | Conditional Go |
| Overall Feasibility | 78.45, Conditional Go | 72.85, Watchlist / Hold | 72.1, Conditional Go |
| Outcome | Prioritise for site due diligence | Strategic reserve | Active alternate |
Preferred site: Crabtree Hill. It is the only site whose substation DCI rates as a suitable voltage class, and it pairs that with the largest capacity estimates and the closest transmission reference of the three. Its binding gap, carrier fiber, has a documented path to resolution: cloud on-ramps, 66 IXPs and a PoP all sit within roughly 14–18 km, so a metro extension is a defined engineering task. The power gaps at the other two sites require voltage upgrades whose scope, cost and date are not available in the assessment.
Why not Winkfield? It fails both Critical dimensions at Watchlist / Hold. A Market score of 95 cannot compensate for a 33 kV substation and a transmission reference 16.25 km away, because market depth does not energise a building.
Why not Sheffield? Sheffield is the only site that clears both Critical dimensions at Conditional Go, which makes it the strongest alternate. But its Power & Grid signal rests on a 66 kV substation below the benchmark and a capacity proxy about 36.8 km away, and its Market & Competition score of 8 gives no documented evidence of demand.
Does the higher score translate into practical suitability? Only partly. Crabtree Hill's 5.6-point lead over Winkfield and 6.35-point lead over Sheffield reflects strong Power & Grid (98), Land & Buildability (93) and Market & Competition (89) scores, yet its Connectivity hold remains unresolved. The score did not make this decision; the power gate did. Note also that Winkfield and Sheffield sit just 0.75 points apart but carry different overall Decision Signals, a reminder that the signal, not the decimal, carries the meaning.
5. How a buyer rule changes the decision
A preferred site is only as robust as the buyer rule most likely to overturn it. The clearest test in the evidence is to make connectivity a hard requirement.
Connectivity as a mandatory gate
Suppose the buyer adds one rule: every Critical dimension must reach Conditional Go or better before diligence spend. Crabtree Hill fails on Connectivity, Winkfield fails on both Power & Grid and Connectivity, and Sheffield becomes the only qualifying site, despite the lowest Overall Feasibility score of the three. The decision changes, but so does the development thesis: per its own report, Sheffield suits an edge or enterprise-led positioning backed by an anchor customer, not speculative hyperscale capacity, and it still needs a high-voltage upgrade from 66 kV.
| Scenario | Preferred site | What drives the outcome |
|---|---|---|
| Base decision logic | Crabtree Hill | Only suitable high-voltage substation; fiber is the first condition to clear |
| Every Critical dimension at Conditional Go or better | Sheffield | Only site with both Power & Grid and Connectivity at Conditional Go |
6. What evidence does the buyer still need?
The reports leave several items unverified. These gaps are not weaknesses of the decision; they define the next stage of work.
Prioritised due-diligence action plan
The action plan below ranks the outstanding evidence by its ability to change the site decision. Ownership is a proposed validation owner unless stated otherwise; the reports do not assign responsibility.
| Evidence required | Site | Responsible party | Next action | Decision impact |
|---|---|---|---|---|
| Firm deliverable capacity, queue position, connection offer and energisation date | All three | Utility provider (proposed) | Commission interconnection studies and request connection offers with dates | Decisive: can reverse the ranking |
| Physically diverse carrier fiber routes, costs and delivery dates | Crabtree Hill, Winkfield | Fiber operators (proposed) | Issue route requests to carriers serving the nearest IXPs and PoPs | Decisive: clears or fails a Critical gate |
| High-voltage upgrade scope from 66 kV and 33 kV | Sheffield, Winkfield | Utility provider (proposed) | Request upgrade scope and delivery timing | Decisive for the alternates |
| Required operational date and target IT load within 10–50 MW | All three | Buyer's technical team (proposed) | Define the start date and load so the timeline test can run | High: enables a start-date test |
| Anchor-customer demand and regional absorption | Sheffield | Buyer's commercial team (proposed) | Test edge or enterprise demand before diligence spend | High: Market & Competition is at Watchlist / Hold |
| Flight path value (blank but rated Red) and aviation safeguarding | Crabtree Hill | Aviation safeguarding authority (proposed) | Confirm corridor status and height limits near Stapleford Aerodrome | Medium |
| Wind-loading criteria (High at all three) and hazardous-industry setback | All three; setback at Winkfield and Sheffield | Buyer's technical team and insurer (proposed) | Set wind design criteria; screen hazardous sites at 6.849 km and 7.837 km | Medium: reports treat these as engineering-mitigable |
| Connection cost allocation and lead times for long-lead equipment such as transformers | All three | Utility provider and buyer's technical team (proposed) | Request cost and equipment schedules alongside the connection offer | High: drives the start-date test |
| Cable route, easements and rights of way for power and fiber | All three | Site developer (proposed) | Map route options and landowners between site, substation and network nodes | High: a blocked route can stall an otherwise suitable site |
| Water supply for cooling, flood and seismic screening | All three | Buyer's technical team (proposed) | Confirm the cooling approach and the water source it requires | Medium |
| Workforce availability and tax or incentive eligibility | All three | Buyer's commercial team (proposed) | Assess local skills and incentive programmes in the next study stage | Low to medium for the technical ranking |
| Planning status, land control and land price | All three | Planning authority and site developer (proposed) | Confirm parcel planning status; reconcile Sheffield's 185 USD/sqm with its rationale, which calls pricing unverified | Medium |
7. What the feasibility study supports
- 01The power gate decides first.A suitable high-voltage substation separates Crabtree Hill from two sites that need voltage upgrades.
- 02A score is not a decision.The 0.75-point gap between Winkfield and Sheffield hides opposite Decision Signals, and the lowest-scoring site is the only one that clears both Critical gates.
- 03The buyer's rules can change the answer.Making connectivity a hard gate moves the preference from Crabtree Hill to Sheffield.
- 04Unknown dates keep every answer provisional.None of the reports documents a connection or energisation date, so the timeline test waits on the utility.
Where this study sits in the full feasibility process
- 01Step 1, site screening and technical feasibilityCompare shortlisted sites on the same brief and pick the one that earns diligence spend. This article completes this step.
- 02Step 2, power and connectivity validationSecure the utility connection offer, upgrade scope, costs and dates, and confirm diverse carrier routes.
- 03Step 3, land control and permittingConfirm the parcel, planning status, environmental consents, easements, water for cooling and backup generation permits.
- 04Step 4, design and engineeringSet the redundancy and design-standard target, phasing and MW per acre for the chosen site.
- 05Step 5, financial feasibilityBuild the revenue, cost and financing case that lenders and investors need. This step requires an independent financial assessment.
Scope disclaimer. This is a technical site feasibility assessment, not a final investment recommendation. DCI scores indicate relative technical suitability based on the evidence available at the assessment date of 6 November 2026. Scores alone do not establish project viability, commercial attractiveness or financial returns. This article does not address construction costs, capital expenditure, revenue projections, operating costs, ROI or investment returns; those require a separately researched, independent financial assessment. Land prices cited here are DCI screening metrics, not cost estimates, and no site in this article is approved, secured, construction-ready or operational.