UK data centre projects by construction stage, location and expected opening date
The UK has 470 operating data centers with 3,543 MW of IT load, 132 phases under construction adding 13,939 MW, and 52 announced schemes worth 15,193 MW. Here is where they are, who is building them, what changed recently, and what an East London AI-ready design looks like.
Published November 25, 2026
- 3,543 MW
- Operating (470 sites)
- 13,939 MW
- Under construction (132 phases)
- 15,193 MW
- Announced (52 schemes)
- 270
- Named operators
- 159
- Towns and cities
- 12
- UK regions
Mordor Intelligence, Data Center Intelligence research team. Updated November 2026.
- London and the South East still run most of the load.The two regions hold 2,559 MW of the 3,543 MW operating (72%). The pipeline is spreading: the South East (7,636 MW), Scotland (6,609 MW), Wales (4,356 MW) and the North East (2,079 MW) hold 20,680 MW under construction or announced.
- The build-out is concentrated in 2027 and 2028.Tracked IT load rises from 3,628 MW in 2026 to 17,548 MW in 2028 if all dated phases arrive on time, compared with an average of about 196 MW of operating load added per year from 2016 to 2026.
- AI-density designs dominate the announced list.51 of 52 announced schemes are designed for 40 kW per rack or more; the median operating UK site is built for 5 kW per rack.
How many UK data center projects does DCI track?
| Status | Count | IT load (MW) | Site power (MW) |
|---|---|---|---|
| Operating | 470 | 3,543.1 | 5,090.0 |
| Under construction | 132 | 13,939.0 | 17,424.3 |
| Announced | 52 | 15,193.2 | 18,516.0 |
| Planned | 14 | – | – |
| Cancelled | 1 | – | – |
| Total | 669 | 32,675.3 | 41,030.3 |
The pipeline dwarfs the installed base. The 29,132 MW under construction or announced is 8.2 times the UK’s operating base. Construction alone, 13,939 MW across 132 phases, equals 3.9 times today’s operating load. Announced schemes are much larger on average, 292 MW per scheme against 106 MW for phases under construction, because many are whole AI campuses on former industrial land.
Data centres in the UK by region
| Region | Operating | Operating (MW) | Under constr. | Under constr. (MW) | Announced | Announced (MW) | Planned |
|---|---|---|---|---|---|---|---|
| South East | 74 | 348.6 | 16 | 2,223.3 | 13 | 5,412.6 | 2 |
| Scotland | 28 | 106.9 | 11 | 3,651.2 | 17 | 2,958.0 | 6 |
| Wales | 10 | 133.0 | 7 | 1,188.6 | 1 | 3,166.9 | 1 |
| London | 190 | 2,210.3 | 39 | 2,704.9 | 4 | 152.7 | 2 |
| East of England | 25 | 90.8 | 31 | 1,590.3 | 5 | 753.6 | 0 |
| North East | 10 | 45.8 | 3 | 1,444.9 | 4 | 634.2 | 0 |
| South West | 24 | 98.2 | 1 | 5.2 | 4 | 1,954.4 | 0 |
| Yorkshire and the Humber | 22 | 41.0 | 11 | 574.5 | 2 | 79.4 | 0 |
| East Midlands | 12 | 266.1 | 6 | 481.3 | 1 | 20.0 | 0 |
| North West | 52 | 137.3 | 4 | 65.6 | 1 | 61.5 | 0 |
| Northern Ireland | 3 | 5.0 | 2 | 4.6 | 0 | 0.0 | 0 |
| West Midlands | 19 | 54.2 | 1 | 4.6 | 0 | 0.0 | 0 |
| Isle of Man (Crown Dependency)* | 1 | 5.9 | 0 | 0.0 | 0 | 0.0 | 0 |
| Region not stated | 0 | 0.0 | 0 | 0.0 | 0 | 0.0 | 3 |
| Total, active records | 470 | 3,543.1 | 132 | 13,939.0 | 52 | 15,193.2 | 14 |
The London-Slough axis. The London region has 190 operating data centers and 2,210 MW of IT load; DCI records 184 of them, 2,126 MW, under Greater London, with Hayes listed separately. The South East adds 74 operating sites and 349 MW, with Slough recorded at 7 sites and 55 MW. Outside the South, Cardiff (7 sites, 131 MW) and Manchester (33 sites, 90 MW) are the main hubs, and AI Pathfinder’s Chelveston site in the East Midlands is the largest single operating site at 250 MW.
Scotland, Wales and the South East take the pipeline. Wales has 4,356 MW in its pipeline against 133 MW operating, led by Maska Group’s 3,167 MW Rhondda Cynon Taf scheme and Anglesey Land Holdings’ 922 MW Holyhead project (recorded in DCI under Greater London; the site is Prosperity Parc, Anglesey). Scotland has 6,609 MW under construction or announced, against 107 MW operating, led by Apatura (1,840 MW across Ravenscraig, Cumnock, Coldstream, Larbert and Ochiltree), Argyll Data Development (1,573 MW in Argyll & Bute), ILI Group (1,251 MW) and AI Pathfinder’s North Ayrshire phase (600 MW). The South East holds the largest pipeline, 7,636 MW, led by Pinewood Group’s 3,554 MW Iver Heath campus and Microsoft’s Langley scheme (1,502 MW in DCI; Microsoft has not published a capacity). The North East (2,079 MW) follows, with QTS at Cambois, Teesworks and Sembcorp on Teesside.
Largest operating locations.
| Location | Operating sites | IT load (MW) |
|---|---|---|
| Greater London | 184 | 2,125.5 |
| Chelveston | 1 | 250.0 |
| Cardiff | 7 | 130.9 |
| Manchester | 33 | 90.2 |
| Hayes | 4 | 66.0 |
| Slough | 7 | 55.1 |
| Glenrothes | 2 | 44.4 |
| Birmingham | 11 | 43.1 |
| Hampshire | 8 | 43.0 |
| Berkshire | 4 | 36.9 |
Leading operators and pipeline developers
| Operator | Operating sites | Operating MW | Share | Pipeline MW |
|---|---|---|---|---|
| Digital Realty | 15 | 274.0 | 8% | – |
| AI Pathfinder | 1 | 250.0 | 7% | 600.0 |
| Equinix | 15 | 243.7 | 7% | 45.4 |
| VIRTUS | 13 | 223.0 | 6% | 107.5 |
| IBM | 10 | 188.1 | 5% | – |
| Ark | 18 | 169.0 | 5% | 396.5 |
| Vantage | 4 | 143.6 | 4% | 136.3 |
| NTT DATA | 8 | 130.3 | 4% | 666.7 |
| AWS | 4 | 109.0 | 3% | 603.3 |
| Colt DCS | 3 | 75.4 | 2% | 705.5 |
No dominant operator. The UK operating market is fragmented: the ten largest operators run 51% of operating IT load, and no operator holds more than 8%. AI Pathfinder’s Chelveston site is the largest single operating site at 250 MW (the same record also carries a 500 MW expansion dated 2027 to 2029), followed by the Digital Realty, Equinix and VIRTUS estates.
Developers lead the pipeline. The pipeline belongs to different names. Pinewood Group (3,554 MW), Maska Group (3,167 MW), Apatura (1,840 MW), Microsoft (1,800 MW), Argyll Data Development (1,573 MW) and ILI Group (1,251 MW) hold the largest pipelines, and 7 of the eight largest pipeline holders have no operating UK site yet. Among established operators, Colt DCS (706 MW), NTT DATA (667 MW) and AWS (603 MW) carry the largest pipelines.
UK data centre projects under construction or announced
11 selected phases from the 132 under construction
| Phase | Operator | Location | Added IT (MW) | Expected | Construction firms named (role where stated) |
|---|---|---|---|---|---|
| Argyll Data Development Scotland DC1 – Other Phases | Argyll Data Development | Argyll & Bute | 1,111.1 | 2028 | None recorded |
| Anglesey Land Holdings DC1 (recorded as Greater London DC1) | Anglesey Land Holdings | Holyhead, Anglesey* | 922.3 | 2030 | None recorded |
| Pinewood Group Iver Heath DC1 – Building 1 | Pinewood Group | Iver Heath | 710.8 | 2028 | None recorded |
| NTT DATA Greater London DC1 | NTT DATA | Greater London | 666.7 | 2030 | None recorded |
| Teesworks AI Data Centre | Teesworks | Middlesbrough | 645.8 | 2030 | None recorded |
| AI Pathfinder North Ayrshire DC1 | AI Pathfinder | North Ayrshire | 600.0 | 2028 | None recorded |
| Cambois Data Center | QTS | Blyth (Cambois) | 571.4 | 2028 | Arcadis; Corgan; Cundall Johnston & Partners; Ridge and Partners; Quod |
| Argyll Data Development Scotland DC1 – Phase 1 | Argyll Data Development | Argyll & Bute | 461.5 | 2027 | None recorded |
| Apatura Ravenscraig | Apatura | Glasgow | 458.3 | 2030 | None recorded |
| Iver DC | AWS | Iver | 394.3 | 2027 | Arup |
| Buckinghamshire Data Center | Thorney Lane LLP | Buckinghamshire | 348.8 | 2029 | None recorded |
Delivery timing: 2 phases (85 MW) are due in Q4 2026 (VIRTUS Buckinghamshire and Kao Data KLON-03); 48 phases (2,471 MW) are due in 2027; and 34 phases (5,845 MW) are scheduled for 2029 or 2030. The largest single phase is Argyll Data Development’s other phases in Argyll & Bute (1,111 MW, 2028), followed by Anglesey Land Holdings’ Holyhead project on Anglesey (922 MW, 2030; DCI records it as Greater London, corrected here to Wales) and Pinewood Group’s Building 1 at Iver Heath (711 MW, 2028).
Contractors. 45 of the 132 phases name at least one firm, covering 3,518 MW. Sweet Project Holdings (17 phases) and Cundall Johnston & Partners (14) appear most often, and the named firms cluster on established programs: Colt DCS, Ark, VIRTUS, QTS, AWS and Ada Infrastructure.
Announced schemes of 200 MW or more
| Scheme | Developer | Location | IT load (MW) | Expected | Rack density (kW) |
|---|---|---|---|---|---|
| Maska Group Rhondda Cynon Taf DC1 | Maska Group | Rhondda Cynon Taf | 3,166.9 | 2028 | 50 |
| Microsoft Langley DC1 | Microsoft | Langley | 1,501.6 | 2028 | 50 |
| Valeon data centre | Xlinks | Devon | 1,219.5 | 2029 | 60 |
| Pinewood Group Iver Heath DC1 - Building 5 | Pinewood Group | Iver Heath | 710.8 | 2032 | 120 |
| Pinewood Group Iver Heath DC1 - Building 2 | Pinewood Group | Iver Heath | 710.8 | 2029 | 120 |
| Pinewood Group Iver Heath DC1 - Building 3 | Pinewood Group | Iver Heath | 710.8 | 2030 | 120 |
| Pinewood Group Iver Heath DC1 - Building 4 | Pinewood Group | Iver Heath | 710.8 | 2031 | 120 |
| Mulberry Property Developments Buckinghamshire DC1 | Mulberry Property Developments | Buckinghamshire | 581.2 | 2029 | 60 |
| Cato Data Centre Campus | ILI Group | Fife | 476.2 | 2028 | 50 |
| Rufus Data Centre Campus | ILI Group | East Ayrshire | 450.0 | 2030 | 75 |
| Bridgewater Mercury Bridgewater DC1 - Building 1 | Bridgewater Mercury | Bridgwater, Somerset | 416.7 | 2030 | 150 |
| Aurelius Data Centre Campus | ILI Group | North Lanarkshire | 325.2 | 2029 | 60 |
| Blyth Data Centre | TBC Partners | Cambois | 250.0 | 2030 | 75 |
| Larbert Data Center | Apatura | Larbert | 243.9 | 2029 | 60 |
| Ochiltree Data Centre | Apatura | Ochiltree | 200.0 | 2028 | 50 |
These are all 15 announced schemes of 200 MW or more (the selection rule for this table). Together they hold 11,674 MW, 77% of the 15,193 MW announced across 52 schemes. None has started construction; Pinewood’s Building 1 (711 MW) is under construction and appears in the table above.
When could new UK data centre capacity open?
| Year | Operating sites | Under construction | Announced | Total |
|---|---|---|---|---|
| 2024 | 3,047.7 | 0.0 | 0.0 | 3,047.7 |
| 2025 | 3,488.8 | 0.0 | 0.0 | 3,488.8 |
| 2026 | 3,543.1 | 85.0 | 0.0 | 3,628.1 |
| 2027 | 3,793.1 | 2,555.5 | 57.7 | 6,406.4 |
| 2028 | 3,793.1 | 7,943.6 | 5,810.9 | 17,547.7 |
| 2029 | 4,043.1 | 10,064.8 | 9,861.0 | 23,969.0 |
| 2030 | 4,043.1 | 13,939.0 | 12,153.8 | 30,136.0 |
A step change in 2027 and 2028. Tracked operating IT load grew from 1,584 MW in 2016 to 3,543 MW in 2026, about 196 MW a year. The dated pipeline would add 2,778 MW in 2027 and a further 11,141 MW in 2028, 57 times the historical yearly pace. 5,811 MW of the 2028 total comes from schemes that have only been announced, so the realistic 2028 figure depends on how many of them start construction in 2026 and 2027.
Recent changes to named UK projects
| Project | Change | Previous | New | Effect on buyer list or yearly capacity |
|---|---|---|---|---|
| Iver DC (AWS) | Approved / pre-construction | Planning application | Full permission granted by Buckinghamshire Council, PL/25/4351/FA (28 Sep 2026) | Recorded under construction; 394.3 MW in 2027 |
| Manor Farm Propco Ltd. Slough DC1 | Approval and capacity | 147 MW proposal | Approved by UK government; 119.5 MW IT load recorded (147 MW ÷ PUE 1.23) (12 Jun 2026) | +119.5 MW in 2029; 147 MW is site power. Probable duplicate of DC-11588 (116.7 MW, under construction) |
| DARE DC Bromley DC1 | New scheme | No record | 50 MW two-building campus proposed on green belt land (28 Jul 2026) | +39.7 MW in 2028; 50 MW is site power |
| CyrusOne Southall DC1 | Planning | Site proposal | Ealing Council planning committee resolution to grant on the former Honey Monster factory site, subject to a s106 agreement and Mayor of London Stage 2 referral (15 Jul 2026) | Planned; no IT load recorded yet |
| DataVita DV1 Expansion and DV3 | Finance | Planned | £300m debt facility in North Lanarkshire (18 Aug 2026) | Planned; no IT load recorded yet |
| University of Edinburgh Edinburgh DC1 | Construction | Planned | Work under way on the £750m national supercomputer (1 Jul 2026) | Planned; no IT load recorded yet |
| Equinix Slough (recorded as Greater London DC1) | Planning | Proposal | Slough Borough Council outline planning permission on former AkzoNobel paint factory site (26 Nov 2025) | Planned; no IT load recorded yet |
| DataVita DV4 | Planning | Pre-application | Revised plans submitted to North Lanarkshire Council (3 Nov 2025) | Planned; no IT load recorded yet |
What the changes mean. 3 of these changes carry dated IT load: Iver DC (394.3 MW, 2027), Manor Farm in Slough (119.5 MW, 2029) and DARE DC in Bromley (39.7 MW, 2028). The others are planning permissions, funding or construction steps on planned records that carry no IT load yet in DCI, so they move projects towards the buyer list without changing expected capacity.
Site power versus IT load. Two changes are about definitions rather than new capacity: the 147 MW Manor Farm scheme in Slough and the 50 MW DARE DC scheme in Bromley were announced in terms of total site power, which equals less IT load once cooling and losses are accounted for.
Planning policy, energy, water, sustainability and reliability
| Affected phase | Developer | Constraint | Date | What must happen next |
|---|---|---|---|---|
| DARE DC Bromley DC1 | DARE DC | Green belt farmland; EIA screening opinion requested | Jul 2026 | Screening opinion, then a planning application and decision |
| SDCL: Cockenzie Campus | SDCL | Feasibility, planning application and public consultation still required | Oct 2025 | Planning application and consultations before any build date |
| CX Technology Campus Building 1 | CX Tech | Planning permission in principle for a 1 GW campus at the former Chapelcross nuclear site (application 26/1649/PIP) | Validated 28 Sep 2026; decision pending | Dumfries and Galloway Council decision (operator targets Dec 2026) before Building 1 (2029) can start |
| DataVita DV4 | DataVita | Plans revised after four public consultation events, then submitted | Nov 2025 | North Lanarkshire planning decision |
| Manor Farm Propco Ltd. Slough DC1 | Manor Farm Propco | Approved by the UK government | 12 Jun 2026 | Construction start to hold the 2029 date |
| Iver DC | AWS | Full permission PL/25/4351/FA granted under delegated powers, subject to conditions and a legal agreement (£600,382 air-quality mitigation; generator emissions monitoring plan) | 28 Sep 2026 | Discharge pre-commencement conditions; record is under construction for 2027 |
| CARBON3AI LIMITED Anglesey DC1 | CARBON3AI LIMITED | Plans put forward on the former Octel chemical works | Jan 2026 | Application and decision; capacity to be stated |
| Slate Island Developments Ltd Greenock DC1 | Slate Island Developments | Data centre and battery storage on the former IBM site | Mar 2026 | Planning application; capacity to be stated |
| Viridor Energy UK (unnamed) | Viridor Energy | Data centres powered by energy-from-waste sites | Jun 2026 | Site-level records and applications |
| DataVita DV1 - Expansion | DataVita | £300m debt facility in the North Lanarkshire AI Growth Zone | Aug 2026 | Construction of DV1 expansion and DV3 |
| University Hospital Southampton Southampton DC1 | University Hospital Southampton | Plans submitted December 2025; rooftop solar | Feb 2026 | Planning decision |
Energy and efficiency. Newer designs target much lower PUE: operating sites average 1.49, phases under construction 1.26 and announced schemes 1.20. That means the 29,132 MW of pipeline IT load needs about 35,940 MW of site power, 23% more than its IT load. Three Apatura schemes in Scotland plan battery energy storage and a new on-site substation as their backup, and the Viridor and Slate Island plans tie new sites to energy-from-waste and battery storage.
Reliability and water. Reliability targets are rising too: 8% of operating sites are Tier 4, against 53% of phases under construction and 92% of announced schemes, with N+1 the most common power and cooling redundancy. Water is becoming a planning issue, particularly in the South East; few UK developers publish water use, so it has to be checked in each planning file.
AI capacity and opportunities for construction firms
| Rack density | Operating | Under construction | Announced | Pipeline IT load (MW) |
|---|---|---|---|---|
| Under 20 kW | 462 | 89 | 1 | 7,856.6 |
| 20–39 kW | 5 | 14 | 0 | 972.8 |
| 40–79 kW | 3 | 24 | 31 | 14,590.7 |
| 80 kW and above | 0 | 5 | 20 | 5,712.1 |
AI density is in the announced list. 80 phases under construction or announced, 20,303 MW, are designed for 40 kW per rack or more, against just 3 operating sites. Clearstone’s Ebbsfleet campus at Dartford rises from 75 kW to 150 kW per rack across four buildings, Pinewood’s Iver Heath buildings are designed for 120 kW and Bridgewater Mercury’s Somerset building for 150 kW. Nscale’s Essex phase (69 MW, 40 kW, 2027) is the main AI cloud build under construction in the South East and East.
Delivery pressure. Delivery pressure comes from scale as much as density. 98 phases under construction are dated by 2028, carrying 8,094 MW, and a further 14 announced schemes (5,838 MW) are also dated by 2028 without having started construction. For these, power connection, planning, and contractor capacity all have to be in place within two years.
Which firms are named on construction projects?
| Firm | Phases | Operators | Added IT (MW) |
|---|---|---|---|
| Sweet Project Holdings | 17 | Ark, Colt DCS | 1,102.0 |
| Cundall Johnston & Partners | 14 | Ada Infrastructure (Ares Management), Colt DCS, Corscale, Kao Data, QTS | 1,628.7 |
| Ridge and Partners | 9 | Colt DCS, QTS | 1,276.9 |
| Arup | 9 | AWS, Colt DCS | 1,099.8 |
| studioNWA | 9 | Colt DCS, VIRTUS | 780.5 |
| Gallagher | 8 | Colt DCS | 705.5 |
| ISG | 8 | Colt DCS | 705.5 |
| Salus Engineering | 8 | Colt DCS | 705.5 |
| Savills | 8 | Colt DCS | 705.5 |
| McLaren Construction | 6 | AWS, Corscale, Microsoft | 388.8 |
Builder opportunities. 87 phases under construction and 51 announced schemes have no publicly named builder. 68 of them are designed for 40 kW per rack or more, carrying 18,831 MW: the strongest openings for main contractors, electrical contractors and liquid-cooling suppliers. Firms that are already named tend to follow one operator across several phases, so winning one building often means winning the campus.
East London design case: Ada Infrastructure’s Docklands campus
| Facility | Status | IT (MW) | Sq ft | Racks | kW/rack | PUE | Tier | Cooling redundancy |
|---|---|---|---|---|---|---|---|---|
| Ada Docklands (each building) | Under construction | 70.0 | 315,000 | 11,500 | 10 | 1.20 | Tier 4 | N+1 |
| London South (Global Switch) | Under construction | 30.0 | 110,000 | 4,500 | 10 | 1.20 | Tier 3 | N+1 |
| London East (Global Switch) | Operating | 39.3 | 141,086 | 5,500 | 4 | 1.20 | Tier 3 | N+1 |
| Telehouse North Two (Telehouse) | Operating | 20.5 | 73,400 | 3,670 | 5 | 1.55 | Tier 3 | N+1 |
| Telehouse West Two (Telehouse) | Under construction | 26.2 | 14,630 | 650 | 40 | 1.26 | Tier 3 | N+1 |
| LD8 (Equinix) | Under construction | 12.0 | 58,537 | 2,927 | 10 | 1.30 | Tier 3 | N+1 |
| Newham Data Center (Legal & General) | Under construction | 53.3 | 88,889 | 8,889 | 10 | 1.30 | Tier 4 | N+1 |
| London 1 Data Center Phase 2 (NTT DATA) | Operating | 32.0 | 156,100 | 7,810 | 10 | 1.33 | Tier 3 | N+1 |
Layout. Each Ada building holds 11,500 racks on 315,000 sq ft, about 27 sq ft per rack. That is in line with Global Switch’s London East and roomier than Telehouse North Two and NTT DATA’s Dagenham phase; Legal & General’s Newham phase is the tightest layout. The new Docklands phases are all designed for 10 kW per rack or more, against 4 to 5 kW in the older Global Switch and Telehouse buildings, while Telehouse West Two is designed for 40 kW.
Density. 11,500 racks at 10 kW would draw 115 MW, compared with 70 MW of IT load per building, averaging about 6.1 kW per rack at full load. The 10 kW figure is best read as a design maximum per rack. Suppliers sizing power and cooling equipment per hall should plan for that peak, not the average.
Questions about UK data centre projects
01
How many data centres are there in the UK?
DCI tracks 669 UK data centre records: 470 operating, 132 under construction, 52 announced, 14 planned and 1 cancelled.
02
How much data centre capacity is under construction in the UK?
13,939.0 MW of IT load across 132 phases, about 17,424 MW of site power. A further 15,193.2 MW is announced.
03
Where are most UK data centres?
London (190 operating sites, 2,210 MW) and the South East. The South East, Scotland and Wales hold the largest shares of the pipeline.
04
Are any UK data centre projects paused or cancelled?
No UK record in DCI is marked as paused as of 17 November 2026 (DCI records only). One record is cancelled: NTT DATA’s Hemel Hempstead 1 (2.1 MW).
05
Does Data Center Intelligence offer a free trial?
Yes. The DCI team starts with a 30-minute walkthrough tailored to your market, then opens a trial for your team.
Explore UK data centre projects in DCI
DCI holds the full UK list with filters for region, operator, status, capacity, rack density, redundancy, and expected year, and tracks status changes on each phase. A demonstration walks through the facilities and projects that match your brief. For a new development, use the DCI site selection tool to compare candidate locations against your project requirements. See how buyers assess locations in the data center site selection guide.
Scheduling takes two minutes. No commitment.