UK data centre projects by construction stage, location and expected opening date

The UK has 470 operating data centers with 3,543 MW of IT load, 132 phases under construction adding 13,939 MW, and 52 announced schemes worth 15,193 MW. Here is where they are, who is building them, what changed recently, and what an East London AI-ready design looks like.

Published November 25, 2026

3,543 MW
Operating (470 sites)
13,939 MW
Under construction (132 phases)
15,193 MW
Announced (52 schemes)
270
Named operators
159
Towns and cities
12
UK regions

Mordor Intelligence, Data Center Intelligence research team. Updated November 2026.

  • London and the South East still run most of the load.
    The two regions hold 2,559 MW of the 3,543 MW operating (72%). The pipeline is spreading: the South East (7,636 MW), Scotland (6,609 MW), Wales (4,356 MW) and the North East (2,079 MW) hold 20,680 MW under construction or announced.
  • The build-out is concentrated in 2027 and 2028.
    Tracked IT load rises from 3,628 MW in 2026 to 17,548 MW in 2028 if all dated phases arrive on time, compared with an average of about 196 MW of operating load added per year from 2016 to 2026.
  • AI-density designs dominate the announced list.
    51 of 52 announced schemes are designed for 40 kW per rack or more; the median operating UK site is built for 5 kW per rack.

How many UK data center projects does DCI track?

Data Center Intelligence (DCI) tracks 669 UK data center records by 270 operators and developers: 470 operating, 132 under construction, 52 announced, 14 planned and 1 cancelled.
UK data centers by status, IT load and total site power
UK data centers by status, IT load and total site power. Capacity totals exclude the cancelled project; its 2.1 MW is stated in the FAQ.
UK data centers by status, IT load and total site power, checked 17 November 2026.
StatusCountIT load (MW)Site power (MW)
Operating4703,543.15,090.0
Under construction13213,939.017,424.3
Announced5215,193.218,516.0
Planned14––
Cancelled1––
Total66932,675.341,030.3

The pipeline dwarfs the installed base. The 29,132 MW under construction or announced is 8.2 times the UK’s operating base. Construction alone, 13,939 MW across 132 phases, equals 3.9 times today’s operating load. Announced schemes are much larger on average, 292 MW per scheme against 106 MW for phases under construction, because many are whole AI campuses on former industrial land.

Data centres in the UK by region

Data centres and IT load (MW) by region and stage. Anglesey Land Holdings’ 922.3 MW Holyhead project is shown under Wales (DCI records it as Greater London). *One operating record (Domicilium, 5.9 MW) is on the Isle of Man, which is not part of the UK; it is kept in the 669-record total and shown separately.
UK data centres and IT load by region and stage, checked 17 November 2026.
RegionOperatingOperating (MW)Under constr.Under constr. (MW)AnnouncedAnnounced (MW)Planned
South East74348.6162,223.3135,412.62
Scotland28106.9113,651.2172,958.06
Wales10133.071,188.613,166.91
London1902,210.3392,704.94152.72
East of England2590.8311,590.35753.60
North East1045.831,444.94634.20
South West2498.215.241,954.40
Yorkshire and the Humber2241.011574.5279.40
East Midlands12266.16481.3120.00
North West52137.3465.6161.50
Northern Ireland35.024.600.00
West Midlands1954.214.600.00
Isle of Man (Crown Dependency)*15.900.000.00
Region not stated00.000.000.03
Total, active records4703,543.113213,939.05215,193.214

The London-Slough axis. The London region has 190 operating data centers and 2,210 MW of IT load; DCI records 184 of them, 2,126 MW, under Greater London, with Hayes listed separately. The South East adds 74 operating sites and 349 MW, with Slough recorded at 7 sites and 55 MW. Outside the South, Cardiff (7 sites, 131 MW) and Manchester (33 sites, 90 MW) are the main hubs, and AI Pathfinder’s Chelveston site in the East Midlands is the largest single operating site at 250 MW.

Scotland, Wales and the South East take the pipeline. Wales has 4,356 MW in its pipeline against 133 MW operating, led by Maska Group’s 3,167 MW Rhondda Cynon Taf scheme and Anglesey Land Holdings’ 922 MW Holyhead project (recorded in DCI under Greater London; the site is Prosperity Parc, Anglesey). Scotland has 6,609 MW under construction or announced, against 107 MW operating, led by Apatura (1,840 MW across Ravenscraig, Cumnock, Coldstream, Larbert and Ochiltree), Argyll Data Development (1,573 MW in Argyll & Bute), ILI Group (1,251 MW) and AI Pathfinder’s North Ayrshire phase (600 MW). The South East holds the largest pipeline, 7,636 MW, led by Pinewood Group’s 3,554 MW Iver Heath campus and Microsoft’s Langley scheme (1,502 MW in DCI; Microsoft has not published a capacity). The North East (2,079 MW) follows, with QTS at Cambois, Teesworks and Sembcorp on Teesside.

Largest operating locations.

Largest UK operating locations by IT load, checked 17 November 2026.
LocationOperating sitesIT load (MW)
Greater London1842,125.5
Chelveston1250.0
Cardiff7130.9
Manchester3390.2
Hayes466.0
Slough755.1
Glenrothes244.4
Birmingham1143.1
Hampshire843.0
Berkshire436.9

Leading operators and pipeline developers

The ten largest operators by operating IT load.
The ten largest UK operators by operating IT load, checked 17 November 2026.
OperatorOperating sitesOperating MWSharePipeline MW
Digital Realty15274.08%–
AI Pathfinder1250.07%600.0
Equinix15243.77%45.4
VIRTUS13223.06%107.5
IBM10188.15%–
Ark18169.05%396.5
Vantage4143.64%136.3
NTT DATA8130.34%666.7
AWS4109.03%603.3
Colt DCS375.42%705.5

No dominant operator. The UK operating market is fragmented: the ten largest operators run 51% of operating IT load, and no operator holds more than 8%. AI Pathfinder’s Chelveston site is the largest single operating site at 250 MW (the same record also carries a 500 MW expansion dated 2027 to 2029), followed by the Digital Realty, Equinix and VIRTUS estates.

Developers lead the pipeline. The pipeline belongs to different names. Pinewood Group (3,554 MW), Maska Group (3,167 MW), Apatura (1,840 MW), Microsoft (1,800 MW), Argyll Data Development (1,573 MW) and ILI Group (1,251 MW) hold the largest pipelines, and 7 of the eight largest pipeline holders have no operating UK site yet. Among established operators, Colt DCS (706 MW), NTT DATA (667 MW) and AWS (603 MW) carry the largest pipelines.

UK data centre projects under construction or announced

This table presents 11 selected phases from the 132 under-construction data centre phases tracked by DCI in the UK. The phases are ranked by expected IT load, based on the DCI datasheet dated 17 November 2026. The remaining 121 phases are included in the overall totals but are not individually listed. Together, the 11 selected phases account for 6,891 MW, representing 49% of the total 13,939 MW under construction. Each row includes the expected opening date and construction firms recorded in DCI. Announced and cancelled projects are categorized separately.

11 selected phases from the 132 under construction

11 selected UK phases from the 132 under construction, ranked by expected IT load, checked 17 November 2026.
PhaseOperatorLocationAdded IT (MW)ExpectedConstruction firms named (role where stated)
Argyll Data Development Scotland DC1 – Other PhasesArgyll Data DevelopmentArgyll & Bute1,111.12028None recorded
Anglesey Land Holdings DC1 (recorded as Greater London DC1)Anglesey Land HoldingsHolyhead, Anglesey*922.32030None recorded
Pinewood Group Iver Heath DC1 – Building 1Pinewood GroupIver Heath710.82028None recorded
NTT DATA Greater London DC1NTT DATAGreater London666.72030None recorded
Teesworks AI Data CentreTeesworksMiddlesbrough645.82030None recorded
AI Pathfinder North Ayrshire DC1AI PathfinderNorth Ayrshire600.02028None recorded
Cambois Data CenterQTSBlyth (Cambois)571.42028Arcadis; Corgan; Cundall Johnston & Partners; Ridge and Partners; Quod
Argyll Data Development Scotland DC1 – Phase 1Argyll Data DevelopmentArgyll & Bute461.52027None recorded
Apatura RavenscraigApaturaGlasgow458.32030None recorded
Iver DCAWSIver394.32027Arup
Buckinghamshire Data CenterThorney Lane LLPBuckinghamshire348.82029None recorded

Delivery timing: 2 phases (85 MW) are due in Q4 2026 (VIRTUS Buckinghamshire and Kao Data KLON-03); 48 phases (2,471 MW) are due in 2027; and 34 phases (5,845 MW) are scheduled for 2029 or 2030. The largest single phase is Argyll Data Development’s other phases in Argyll & Bute (1,111 MW, 2028), followed by Anglesey Land Holdings’ Holyhead project on Anglesey (922 MW, 2030; DCI records it as Greater London, corrected here to Wales) and Pinewood Group’s Building 1 at Iver Heath (711 MW, 2028).

Contractors. 45 of the 132 phases name at least one firm, covering 3,518 MW. Sweet Project Holdings (17 phases) and Cundall Johnston & Partners (14) appear most often, and the named firms cluster on established programs: Colt DCS, Ark, VIRTUS, QTS, AWS and Ada Infrastructure.

Announced schemes of 200 MW or more

UK announced schemes of 200 MW or more, checked 17 November 2026.
SchemeDeveloperLocationIT load (MW)ExpectedRack density (kW)
Maska Group Rhondda Cynon Taf DC1Maska GroupRhondda Cynon Taf3,166.9202850
Microsoft Langley DC1MicrosoftLangley1,501.6202850
Valeon data centreXlinksDevon1,219.5202960
Pinewood Group Iver Heath DC1 - Building 5Pinewood GroupIver Heath710.82032120
Pinewood Group Iver Heath DC1 - Building 2Pinewood GroupIver Heath710.82029120
Pinewood Group Iver Heath DC1 - Building 3Pinewood GroupIver Heath710.82030120
Pinewood Group Iver Heath DC1 - Building 4Pinewood GroupIver Heath710.82031120
Mulberry Property Developments Buckinghamshire DC1Mulberry Property DevelopmentsBuckinghamshire581.2202960
Cato Data Centre CampusILI GroupFife476.2202850
Rufus Data Centre CampusILI GroupEast Ayrshire450.0203075
Bridgewater Mercury Bridgewater DC1 - Building 1Bridgewater MercuryBridgwater, Somerset416.72030150
Aurelius Data Centre CampusILI GroupNorth Lanarkshire325.2202960
Blyth Data CentreTBC PartnersCambois250.0203075
Larbert Data CenterApaturaLarbert243.9202960
Ochiltree Data CentreApaturaOchiltree200.0202850

These are all 15 announced schemes of 200 MW or more (the selection rule for this table). Together they hold 11,674 MW, 77% of the 15,193 MW announced across 52 schemes. None has started construction; Pinewood’s Building 1 (711 MW) is under construction and appears in the table above.

When could new UK data centre capacity open?

Expected additional UK IT load by target year: under construction versus announced (MW). All years are developer or DCI target dates, not confirmed openings.
Tracked UK IT load by target year
Tracked UK IT load by target year, cumulative, if every dated phase is delivered on time (MW). Operating includes the 500 MW expansion recorded on AI Pathfinder’s Chelveston record.
Tracked UK IT load by target year, cumulative, checked 17 November 2026.
YearOperating sitesUnder constructionAnnouncedTotal
20243,047.70.00.03,047.7
20253,488.80.00.03,488.8
20263,543.185.00.03,628.1
20273,793.12,555.557.76,406.4
20283,793.17,943.65,810.917,547.7
20294,043.110,064.89,861.023,969.0
20304,043.113,939.012,153.830,136.0

A step change in 2027 and 2028. Tracked operating IT load grew from 1,584 MW in 2016 to 3,543 MW in 2026, about 196 MW a year. The dated pipeline would add 2,778 MW in 2027 and a further 11,141 MW in 2028, 57 times the historical yearly pace. 5,811 MW of the 2028 total comes from schemes that have only been announced, so the realistic 2028 figure depends on how many of them start construction in 2026 and 2027.

Recent changes to named UK projects

Selected recent changes: 8 of the 16 dated signals on UK records in DCI (DataVita DV1 and DV3 share one row), plus the Iver DC planning decision. The date of each change is shown.
Selected recent changes to named UK projects
Selected recent changes to named UK projects, checked 17 November 2026.
ProjectChangePreviousNewEffect on buyer list or yearly capacity
Iver DC (AWS)Approved / pre-constructionPlanning applicationFull permission granted by Buckinghamshire Council, PL/25/4351/FA (28 Sep 2026)Recorded under construction; 394.3 MW in 2027
Manor Farm Propco Ltd. Slough DC1Approval and capacity147 MW proposalApproved by UK government; 119.5 MW IT load recorded (147 MW ÷ PUE 1.23) (12 Jun 2026)+119.5 MW in 2029; 147 MW is site power. Probable duplicate of DC-11588 (116.7 MW, under construction)
DARE DC Bromley DC1New schemeNo record50 MW two-building campus proposed on green belt land (28 Jul 2026)+39.7 MW in 2028; 50 MW is site power
CyrusOne Southall DC1PlanningSite proposalEaling Council planning committee resolution to grant on the former Honey Monster factory site, subject to a s106 agreement and Mayor of London Stage 2 referral (15 Jul 2026)Planned; no IT load recorded yet
DataVita DV1 Expansion and DV3FinancePlanned£300m debt facility in North Lanarkshire (18 Aug 2026)Planned; no IT load recorded yet
University of Edinburgh Edinburgh DC1ConstructionPlannedWork under way on the £750m national supercomputer (1 Jul 2026)Planned; no IT load recorded yet
Equinix Slough (recorded as Greater London DC1)PlanningProposalSlough Borough Council outline planning permission on former AkzoNobel paint factory site (26 Nov 2025)Planned; no IT load recorded yet
DataVita DV4PlanningPre-applicationRevised plans submitted to North Lanarkshire Council (3 Nov 2025)Planned; no IT load recorded yet

What the changes mean. 3 of these changes carry dated IT load: Iver DC (394.3 MW, 2027), Manor Farm in Slough (119.5 MW, 2029) and DARE DC in Bromley (39.7 MW, 2028). The others are planning permissions, funding or construction steps on planned records that carry no IT load yet in DCI, so they move projects towards the buyer list without changing expected capacity.

Site power versus IT load. Two changes are about definitions rather than new capacity: the 147 MW Manor Farm scheme in Slough and the 50 MW DARE DC scheme in Bromley were announced in terms of total site power, which equals less IT load once cooling and losses are accounted for.

Planning policy, energy, water, sustainability and reliability

Planning, power and site history shape which UK schemes reach construction. The projects below have a documented constraint or approval step, with the phase it affects and what must happen next.
Planning and delivery constraints on named projects
Planning and delivery constraints on named projects. Dates are the planning or signal date recorded for each project; the two named decisions are from Buckinghamshire Council (Iver DC) and Dumfries and Galloway Council (CX Technology Campus).
Planning and delivery constraints on named UK projects, checked 17 November 2026.
Affected phaseDeveloperConstraintDateWhat must happen next
DARE DC Bromley DC1DARE DCGreen belt farmland; EIA screening opinion requestedJul 2026Screening opinion, then a planning application and decision
SDCL: Cockenzie CampusSDCLFeasibility, planning application and public consultation still requiredOct 2025Planning application and consultations before any build date
CX Technology Campus Building 1CX TechPlanning permission in principle for a 1 GW campus at the former Chapelcross nuclear site (application 26/1649/PIP)Validated 28 Sep 2026; decision pendingDumfries and Galloway Council decision (operator targets Dec 2026) before Building 1 (2029) can start
DataVita DV4DataVitaPlans revised after four public consultation events, then submittedNov 2025North Lanarkshire planning decision
Manor Farm Propco Ltd. Slough DC1Manor Farm PropcoApproved by the UK government12 Jun 2026Construction start to hold the 2029 date
Iver DCAWSFull permission PL/25/4351/FA granted under delegated powers, subject to conditions and a legal agreement (£600,382 air-quality mitigation; generator emissions monitoring plan)28 Sep 2026Discharge pre-commencement conditions; record is under construction for 2027
CARBON3AI LIMITED Anglesey DC1CARBON3AI LIMITEDPlans put forward on the former Octel chemical worksJan 2026Application and decision; capacity to be stated
Slate Island Developments Ltd Greenock DC1Slate Island DevelopmentsData centre and battery storage on the former IBM siteMar 2026Planning application; capacity to be stated
Viridor Energy UK (unnamed)Viridor EnergyData centres powered by energy-from-waste sitesJun 2026Site-level records and applications
DataVita DV1 - ExpansionDataVita£300m debt facility in the North Lanarkshire AI Growth ZoneAug 2026Construction of DV1 expansion and DV3
University Hospital Southampton Southampton DC1University Hospital SouthamptonPlans submitted December 2025; rooftop solarFeb 2026Planning decision

Energy and efficiency. Newer designs target much lower PUE: operating sites average 1.49, phases under construction 1.26 and announced schemes 1.20. That means the 29,132 MW of pipeline IT load needs about 35,940 MW of site power, 23% more than its IT load. Three Apatura schemes in Scotland plan battery energy storage and a new on-site substation as their backup, and the Viridor and Slate Island plans tie new sites to energy-from-waste and battery storage.

Reliability and water. Reliability targets are rising too: 8% of operating sites are Tier 4, against 53% of phases under construction and 92% of announced schemes, with N+1 the most common power and cooling redundancy. Water is becoming a planning issue, particularly in the South East; few UK developers publish water use, so it has to be checked in each planning file.

AI capacity and opportunities for construction firms

Data centres by rack density and stage.
UK data centres by rack density and stage, checked 17 November 2026.
Rack densityOperatingUnder constructionAnnouncedPipeline IT load (MW)
Under 20 kW4628917,856.6
20–39 kW5140972.8
40–79 kW3243114,590.7
80 kW and above05205,712.1

AI density is in the announced list. 80 phases under construction or announced, 20,303 MW, are designed for 40 kW per rack or more, against just 3 operating sites. Clearstone’s Ebbsfleet campus at Dartford rises from 75 kW to 150 kW per rack across four buildings, Pinewood’s Iver Heath buildings are designed for 120 kW and Bridgewater Mercury’s Somerset building for 150 kW. Nscale’s Essex phase (69 MW, 40 kW, 2027) is the main AI cloud build under construction in the South East and East.

Delivery pressure. Delivery pressure comes from scale as much as density. 98 phases under construction are dated by 2028, carrying 8,094 MW, and a further 14 announced schemes (5,838 MW) are also dated by 2028 without having started construction. For these, power connection, planning, and contractor capacity all have to be in place within two years.

Which firms are named on construction projects?

Firms named on UK construction projects, checked 17 November 2026.
FirmPhasesOperatorsAdded IT (MW)
Sweet Project Holdings17Ark, Colt DCS1,102.0
Cundall Johnston & Partners14Ada Infrastructure (Ares Management), Colt DCS, Corscale, Kao Data, QTS1,628.7
Ridge and Partners9Colt DCS, QTS1,276.9
Arup9AWS, Colt DCS1,099.8
studioNWA9Colt DCS, VIRTUS780.5
Gallagher8Colt DCS705.5
ISG8Colt DCS705.5
Salus Engineering8Colt DCS705.5
Savills8Colt DCS705.5
McLaren Construction6AWS, Corscale, Microsoft388.8

Builder opportunities. 87 phases under construction and 51 announced schemes have no publicly named builder. 68 of them are designed for 40 kW per rack or more, carrying 18,831 MW: the strongest openings for main contractors, electrical contractors and liquid-cooling suppliers. Firms that are already named tend to follow one operator across several phases, so winning one building often means winning the campus.

East London design case: Ada Infrastructure’s Docklands campus

Ada Infrastructure’s Docklands Data Center at Silvertown (E16) is the largest construction project in East London: three buildings of 70 MW each, totaling 210 MW, with the first 70 MW building due by mid-2028 and the others phased after that, with Cundall and TTSP Architects on the design team. Here is how its design compares with existing and new Docklands facilities.
Ada Docklands compared with other East London data centres
Ada Docklands compared with other East London data centres.
Ada Docklands compared with other East London data centres, checked 17 November 2026.
FacilityStatusIT (MW)Sq ftRackskW/rackPUETierCooling redundancy
Ada Docklands (each building)Under construction70.0315,00011,500101.20Tier 4N+1
London South (Global Switch)Under construction30.0110,0004,500101.20Tier 3N+1
London East (Global Switch)Operating39.3141,0865,50041.20Tier 3N+1
Telehouse North Two (Telehouse)Operating20.573,4003,67051.55Tier 3N+1
Telehouse West Two (Telehouse)Under construction26.214,630650401.26Tier 3N+1
LD8 (Equinix)Under construction12.058,5372,927101.30Tier 3N+1
Newham Data Center (Legal & General)Under construction53.388,8898,889101.30Tier 4N+1
London 1 Data Center Phase 2 (NTT DATA)Operating32.0156,1007,810101.33Tier 3N+1

Layout. Each Ada building holds 11,500 racks on 315,000 sq ft, about 27 sq ft per rack. That is in line with Global Switch’s London East and roomier than Telehouse North Two and NTT DATA’s Dagenham phase; Legal & General’s Newham phase is the tightest layout. The new Docklands phases are all designed for 10 kW per rack or more, against 4 to 5 kW in the older Global Switch and Telehouse buildings, while Telehouse West Two is designed for 40 kW.

Density. 11,500 racks at 10 kW would draw 115 MW, compared with 70 MW of IT load per building, averaging about 6.1 kW per rack at full load. The 10 kW figure is best read as a design maximum per rack. Suppliers sizing power and cooling equipment per hall should plan for that peak, not the average.

Questions about UK data centre projects

  • 01

    How many data centres are there in the UK?

    DCI tracks 669 UK data centre records: 470 operating, 132 under construction, 52 announced, 14 planned and 1 cancelled.

  • 02

    How much data centre capacity is under construction in the UK?

    13,939.0 MW of IT load across 132 phases, about 17,424 MW of site power. A further 15,193.2 MW is announced.

  • 03

    Where are most UK data centres?

    London (190 operating sites, 2,210 MW) and the South East. The South East, Scotland and Wales hold the largest shares of the pipeline.

  • 04

    Are any UK data centre projects paused or cancelled?

    No UK record in DCI is marked as paused as of 17 November 2026 (DCI records only). One record is cancelled: NTT DATA’s Hemel Hempstead 1 (2.1 MW).

  • 05

    Does Data Center Intelligence offer a free trial?

    Yes. The DCI team starts with a 30-minute walkthrough tailored to your market, then opens a trial for your team.

Explore UK data centre projects in DCI

DCI holds the full UK list with filters for region, operator, status, capacity, rack density, redundancy, and expected year, and tracks status changes on each phase. A demonstration walks through the facilities and projects that match your brief. For a new development, use the DCI site selection tool to compare candidate locations against your project requirements. See how buyers assess locations in the data center site selection guide.

Scheduling takes two minutes. No commitment.