List of data centers in Malaysia: operators, status, IT load and cooling

Malaysia runs 1,315.1 MW of IT load today, and Data Center Intelligence tracks 8,892.2 MW more under construction or announced. Johor holds 52.8% of that pipeline, and the 2026 and 2027 delivery calendar decides how much of it arrives on time.

Published November 20, 2026

132 · 1,315.1 MW
Operating projects
72 · 5,954.7 MW
Under construction
27 · 2,937.5 MW
Announced
98
Operators
37
Cities and localities

Mordor Intelligence, Data Center Intelligence research team. DCI projects extracted 4 November 2026.

Malaysia data center projects by status: more capacity is planned than is operating

Malaysia's data center market runs on a small operating base and carries a large order book. Data Center Intelligence (DCI) tracks 232 Malaysian projects: 132 operating, 72 under construction, 27 announced and 1 cancelled. The under-construction and announced pipeline stands at 6.8 times the operating base.
Four features shape the market. Johor holds 52.8% of the pipeline and has overtaken Selangor and Kuala Lumpur combined in operating capacity. Operators build every one of the 99 projects under construction or announced to Tier 3 or Tier 4. Colocation providers carry 77.2% of the pipeline. DCI projects liquid cooling for 53 of the 72 projects under construction. Delivery remains the open question: five projects make up 75% of the 1,361.1 MW due in Q4 2026, and DCI dates 2,932.4 MW more to 2027.

25 selected data center projects in Malaysia

Facility, operator, city and commissioning year for 25 of DCI's 232 tracked Malaysian projects.
25 selected Malaysian data center projects by commissioning year, as of 4 November 2026.
FacilityOperatorCityYear of Commission
Sime Darby Cyberjaya DC1Sime Darby Property BerhadCyberjaya2026
Cyberjaya 1Infinaxis Capital Management Pte. Ltd.Cyberjaya2025
Open DC - PE2Open DC Sdn BhdBayan Lepas2025
Open DC D8-1 Data CentreOpen DC Sdn BhdBukit Kayu Hitam2026
KL1 Phase 1NEXTDC LimitedPetaling Jaya2026
GP3 Phase 1ZDATA Technologies Co., Ltd. (Stratus Technology)Johor Bahru2026
Iskandar Puteri Data Centre (IPDC) Block 2 (West Wing)Telekom Malaysia BerhadIskandar Puteri2025
Klang Valley Data Centre (KVDC) Block 2 (West Wing)Telekom Malaysia BerhadCyberjaya2026
KL1 Phase 2NEXTDC LimitedPetaling Jaya2026
KUL10Digital Realty Trust Inc.Cyberjaya2026
YTL Johor Data Center 6YTL Data Center Holdings Pte. Ltd.Johor Bahru2028
EC32 PenangEdge Centres Pty LtdPenang2027
TM NxeraSingapore Telecommunications Ltd (Nxera)Johor Bahru2026
Johor Campus - Phase 1STACK INFRASTRUCTUREIskandar Puteri2026
Johor Campus - Phase 2STACK INFRASTRUCTUREIskandar Puteri2028
Huawei Cloud Computing Technologies Co., Ltd. (in a partnership with Hatten Land) Melaka DC1Huawei Cloud Computing Technologies Co., Ltd.Melaka2028
Kuala Lumpur DCMicrosoft CorporationKuala Lumpur2028
Bintulu AI Data CenterMaNaDr Pte LtdBintulu2028
JHB4AirTrunk Operating Pty LtdJohor Bahru2028
SQDC Cyberjaya Data CenterSIC Quantum Data Centre Sdn Bhd (SQDC)Cyberjaya2028
GDC-MLK1 Phase 1Global Data Infrastructure Sdn BhdMasjid Tanah2028
GDC-MLK1 Phase 2Global Data Infrastructure Sdn BhdMasjid Tanah2028
GDC-MLK1 Phase 3Global Data Infrastructure Sdn BhdMasjid Tanah2029
Kota Seri Langat Data Center CampusGlobal Data Infrastructure Sdn BhdBanting2029
China Mobile International (Malaysia) Sdn Bhd Port Dickson DC1China Mobile International (Malaysia) Sdn BhdPort Dickson2028

DCI holds the full Malaysian project list, with filters for city, operator, status, capacity band and cooling.

Which operating data center projects have the largest IT loads?

The median operating project with a projected load runs at 2.54 MW, and 115 of the 132 operating projects sit under 20 MW. Selangor hosts 67 of them; 53 of those run under 10 MW, and their operators commissioned 44 before 2018. The ten largest operating projects hold 51% of operating IT load, and Johor hosts eight of the ten. The ten largest operating projects, ranked by IT load.
The ten largest operating Malaysian data center projects by IT load, as of 4 November 2026.
FacilityOperatorCityIT load (MW)TierCoolingCommissioned
MN Holdings Bhd Johor Bahru DC1MN and DC-Science CoJohor Bahru85.73Air2024
MY-01BRIGHTRAYJohor Bahru85.03Air, fan wallsQ2 2025
MY06 Phase 2Bridge Data CentresJohor Bahru80.93Liquid, direct-to-chipQ3 2025
MY02Bridge Data CentresCyberjaya75.53Liquid, direct-to-chip2018
Nusajaya 1, 2, 3 data centers (NTP1, 2, 3)DayOneJohor Bahru69.53Liquid, direct-to-chip2023
SKALI SerdangSKALI Managed E-BusinessSerdang63.33Air2000
K2 Strategic Pte Ltd Johor Bahru DC1K2 StrategicKulai60.03Liquid, immersion2024
JH1 Phase 1Princeton Digital GroupJohor Bahru52.04Liquid, rear-door2024
YTL Green Data Center Park — First Data CenterYTLKulai51.43Air, room-based2024
GP3 Phase 1ZDATA Technologies CoJohor Bahru45.13Air, room-basedQ2 2026

New capacity moves up the tier scale

Tier 1 and Tier 2 facilities make up 67 of the 132 operating projects, yet none of the 99 projects under construction or announced falls in those tiers. Every new project in the Malaysian pipeline targets Tier 3 or Tier 4.

Malaysia's major data center hotspots: Johor leads, the Klang Valley follows

Johor overtook the Klang Valley in 2025

Johor runs 24 operating projects and 701.7 MW of current IT load. Selangor and Kuala Lumpur together run 90 projects and 569.3 MW. DCI's yearly projections show the order reversing during 2025: Johor ended 2024 behind, at 435.7 MW against 476.9 MW, and ended 2025 ahead, at 656.6 MW against 540.2 MW. The sites differ in kind. Among projects with a projected load, the average Johor site runs at 30.5 MW and the average Selangor site at 7.0 MW.
The pipeline widens Johor's lead. Johor has 4,691.5 MW under construction or announced, against 3,124.1 MW for Selangor and Kuala Lumpur together. Selangor still hosts the most operating projects, 67, but small, older halls make up most of them.

Where the pipeline is concentrated, by state

Projects by state, ranked by pipeline IT load.
Malaysian data center projects by state, ranked by pipeline IT load, as of 4 November 2026.
StateOperating projectsOperating IT load (MW)Under construction (MW)Announced (MW)Share of pipeline
Johor24701.73,432.41,259.152.8%
Selangor67456.01,722.6552.525.6%
Kuala Lumpur23113.3634.0215.09.5%
Melaka———335.53.8%
Negeri Sembilan211.0100.0428.15.9%
Sarawak516.8—142.31.6%
Other states1116.365.75.00.8%

A handful of cities carry the data center pipeline

Within the states, a few cities concentrate the pipeline. Johor Bahru, Kulai and Iskandar Puteri hold most of Johor's, and Cyberjaya holds most of Selangor's. Johor Bahru leads on combined capacity, at 3,000.2 MW across 49 projects, and Cyberjaya leads on project count, with 62. Kulai, with 8 projects and 1,509.5 MW, hosts YTL's Sedenak Tech Park West campus.
New hotspots form outside the two leading regions. Melaka has 7 announced projects at 335.5 MW and none under construction. Sarawak has 3 announced projects at 142.3 MW, about 8.5 times its operating base of 16.8 MW. In Selangor, Banting enters the list with no operating capacity and 341.5 MW in the pipeline.

Where the pipeline is concentrated

Cities ranked by combined operating and pipeline IT load.
Malaysian cities ranked by combined operating and pipeline IT load, as of 4 November 2026.
CityStateProjectsOperating IT load (MW)Pipeline IT load (MW)Combined (MW)
Johor BahruJohor49539.32,460.93,000.2
CyberjayaSelangor62287.91,375.81,663.7
KulaiJohor8131.41,378.11,509.5
Kuala LumpurKuala Lumpur32112.3849.0961.3
Iskandar PuteriJohor815.0756.6771.6
Port DicksonNegeri Sembilan1—350350
BantingSelangor2—341.5341.5
MelakaMelaka7—335.5335.5
ElminaSelangor170250.3320.3

To see how buyers assess power, connectivity and land when choosing a site, read our data center site selection guide.

Data centers in Malaysia: colocation providers, cloud operators and cooling systems

Colocation providers and three cloud companies carry the build

Colocation providers carry 77.2% of pipeline IT load (6,866.1 of 8,892.2 MW). Cloud providers building for themselves hold 1,580.9 MW in the pipeline across 12 projects: Google 600.3 MW, Microsoft 465.7 MW and Amazon Web Services 450.0 MW, with Alibaba Cloud and Huawei Cloud making up the rest. Ten operators hold 54% of tracked IT load.
YTL leads all operators with 1,170.2 MW across 6 projects, and its announced Sedenak Tech Park West campus accounts for 975.6 MW of that. Microsoft and Amazon Web Services enter from a standing start: none runs operating capacity in DCI, and both build entirely in the pipeline. Bridge Data Centres runs the largest operating base among the ten largest operators, at 214.4 MW.

The ten largest operators, ranked by combined IT load

The ten largest operators in Malaysia, ranked by combined IT load, as of 4 November 2026.
OperatorProjectsOperating IT load (MW)Pipeline IT load (MW)Combined (MW)
YTL674.61,095.61,170.2
Google370600.3670.3
AirTrunk543.5562.3605.8
Microsoft30465.7465.7
Amazon Web Services40450.0450.0
EdgeConneX40444.0444.0
Racks Central30440.0440.0
Princeton Digital Group352.0318.0370.0
Bridge Data Centres9214.4135.0349.4
Vantage Data Centers556.0292.3348.3

DCI expects most data centers under construction in Malaysia to use liquid cooling

DCI projects liquid cooling for 53 of the 72 projects under construction (74%) and 21 of the 27 announced projects. Among operating projects the share falls to 34 of 132 (26%): 19 of 32 projects dated 2023 or later, against 6 of 80 dated before 2018. Each newer vintage of capacity leans further toward liquid.
Operators use several liquid methods. Among the ten largest operating projects, Bridge Data Centres and DayOne run direct-to-chip cooling, K2 Strategic runs immersion cooling in Kulai, and Princeton Digital Group runs rear-door cooling at JH1 Phase 1. In the pipeline, YTL, Global Telecommunications, Digital Cosmos Malaysia and AirTrunk specify direct-to-chip cooling for large campuses. Air cooling holds on at a few large sites: Empyrion DC plans room-based air cooling for its 200.0 MW MY1 Johor Data Centre, Racks Central plans air for the 175.0 MW RCJM2A Data Centre, and Amazon Web Services plans air for the 150.0 MW KUL - Dengkil project.
DCI reads the shift as a feature of the pipeline's mix: 33 projects of 100 MW or more hold 74% of the pipeline, and large campuses lean to liquid cooling. This is an inference from the projects.
For cooling suppliers, the buyer mostly remains unnamed. Of the 44 liquid-cooled projects under construction at 20 MW or more, 5 name an EPC or general contractor and 3 name the cooling method.
Malaysian projects under construction, filtered by size, cooling and contractor disclosure, as of 4 November 2026.
Filter on projects under constructionProjectsExpected IT load (MW)
20 MW or more555,777.9
20 MW or more, liquid cooling projected444,645.4
20 MW or more, liquid cooling, due Q4 2026101,243.4
20 MW or more, liquid cooling, EPC or general contractor on project5851.5
20 MW or more, air cooled111,132.4
DCI lists each of these projects by name, with operator, city, expected year, cooling and the contractor roles on each project.
Named EPC/general contractor roles DCI has on file for liquid-cooled Malaysian projects under construction, as of 4 November 2026.
OperatorContractorFacilityCooling Status
YTL Data Center Holdings Pte. Ltd.Obayashi CorporationYTL Johor Data Center 6Liquid - Cooled

Data center projects in Malaysia: under construction or announced

Five large data centers under construction in Malaysia

The five largest of the 72 projects under construction add about 1,300+ MW of the IT load under construction, and Johor and Selangor host most of them. Google leads with Malaysia Data Center in Port Dickson at 350 MW, dated to 2030. Sime Darby Property follows with Sime Darby Cyberjaya DC1 at 327.2 MW. Size defines the pipeline: 33 projects of 100 MW or more hold 74% of it.
The five largest projects under construction.
The five largest Malaysian data center projects under construction, as of 4 November 2026.
FacilityOperatorCityExpected IT load (MW)Expected yearCooling
Malaysia Data CenterGooglePort Dickson3502030Liquid
Sime Darby Cyberjaya DC1Sime Darby PropertyCyberjaya327.2Q4 2026Liquid
JHB2AirTrunkIskandar Puteri270.02028Liquid
Vantage Cyberjaya KUL2 Data Center CampusVantage Data CentersCyberjaya256.0Q4 2026Liquid
Digital Hyperspace Malaysia Johor Bahru DC1Digital Hyperspace MalaysiaJohor Bahru232.72027Liquid

Which announced projects have the largest planned IT loads?

Announced projects add 2,937.5 MW. Each carries a public statement from the operator or a partner. YTL's Sedenak Tech Park West Data Center Campus in Kulai accounts for 975.6 MW, 33.2% of the total, and carries a 2029 commissioning year. Melaka and Sarawak enter the pipeline through announced projects: DPS Resources plans 170.0 MW in Melaka for 2027, and MaNaDr plans the 119.1 MW Bintulu AI Data Center for 2028.
The ten largest announced projects.
The ten largest announced Malaysian data center projects, as of 4 November 2026.
FacilityOperatorCityExpected yearCooling
Sedenak Tech Park West Data Center CampusYTLKulai2029Liquid, direct-to-chip
GDC BantingGlobal TelecommunicationsBanting2029Liquid, direct-to-chip
Kota Seri Langat Data Center CampusGlobal Data InfrastructureBanting2029Liquid
DPS Resources Sdn Bhd Melaka DC1DPS ResourcesMelaka2027Liquid
KUL - DengkilAmazon Web ServicesKuala Lumpur—Air
Digital Cosmos CyberjayaDigital Cosmos MalaysiaCyberjaya2028Liquid, direct-to-chip
Bintulu AI Data CenterMaNaDrBintulu2028Liquid
JHB4AirTrunkJohor Bahru2028Liquid
JHB3AirTrunkJohor Bahru2027Liquid, direct-to-chip
Bukit Rambai Data Center Phase 2DPS ResourcesMelaka2030Liquid, direct-to-chip

When is new data center capacity due in Malaysia?

Operating projects added 312.5 MW in 2024 and 299.8 MW in 2025. DCI dates projects under construction to add 1,361.1 MW in 2026 and 2,932.4 MW in 2027, 4.5 and 9.8 times the 2025 pace. Seventeen projects fall due in Q4 2026, and the five largest hold 75% of that quarter's 1,361.1 MW. A slip in any of the three largest moves 200 MW or more into 2027.
Q4 2026 gives the first test of the calendar. Three of the six largest projects under construction — Sime Darby Cyberjaya DC1, Vantage Cyberjaya KUL2 and EdgeConneX's Cyberjaya Data Center — carry Q4 2026 dates, and ten liquid-cooled projects of 20 MW or more, worth 1,243.4 MW, fall due in the same quarter.
Expected capacity by year (MW)
Under constructionAnnounced
Malaysian data center IT load added and due, by year and status, as of 4 November 2026.
YearOperating, added in year (MW)Under construction, due (MW)Announced, due (MW)
202389.5——
2024312.5——
2025299.8——
2026 (to date)82.21,361.1—
2027—2,932.4424.8
2028—941.8600.7
2029—182.01,349.6
2030—537.357.5

Operating additions show the year-on-year change in each operating project's projected IT load; the table leaves out 4 operating projects with no current load. The table does not show two announced projects with no expected year (155.0 MW).

Beyond 2027, announced projects take over the calendar and peak at 1,349.6 MW in 2029, the year YTL dates its Sedenak Tech Park West campus. Operating plus under-construction IT load in DCI totals 7,269.7 MW. No announced project shows a construction start, so DCI reads the 2,937.5 MW of announced capacity as the part of the pipeline with the most timing risk.

Questions about data centers in Malaysia

  • 01

    How many data centers are in Malaysia?

    DCI tracks 232 Malaysian project records: 132 operating, 72 under construction, 27 announced and 1 cancelled. A project record is one campus, building or phase — DCI does not double-count a campus against its individual buildings or phases. Grouping the 231 active records by operator and city yields 157 combinations, a measure of how spread out operators are across cities, not a count of physical facilities.

  • 02

    Which Malaysian state has the most operating data center capacity?

    Johor leads on operating IT load, with 701.7 MW across 24 projects, ahead of Selangor with 456.0 MW. Johor also holds 52.8% of the IT load under construction and announced.

  • 03

    Which Malaysian cities have the most data center projects?

    Cyberjaya hosts 62 projects, Johor Bahru 49 and Kuala Lumpur 32. The projects span 12 states and federal territories.

  • 04

    Who is building Malaysia's new data centers?

    Colocation providers carry 77.2% of pipeline IT load. Cloud providers building for themselves hold 1,580.9 MW across 12 projects, led by Google, Microsoft and Amazon Web Services. YTL leads all operators, with 1,170.2 MW across 6 projects.

  • 05

    Which operators use liquid cooling in Malaysia?

    DCI projects liquid cooling for 34 operating projects, 53 projects under construction and 21 announced projects. Bridge Data Centres runs the most operating liquid-cooled projects (5), followed by AIMS (3), Digital Realty Trust (3), Telekom Malaysia (3), Equinix (2), Open DC (2), Vantage Data Centers (2) and AirTrunk (1).

  • 06

    How much new data center capacity is due in Malaysia during 2026 and 2027?

    DCI dates projects under construction to add 1,361.1 MW in 2026 and 2,932.4 MW in 2027, against 1,315.1 MW in operation today.

  • 07

    Does Data Center Intelligence offer a free trial?

    Yes. The DCI team starts with a 30-minute walkthrough tailored to the market, then opens a trial for the team.

Explore the full Malaysia data center list in DCI

DCI holds the full Malaysian list with filters for city, operator, status, capacity band and cooling. A demonstration walks through the facilities and projects that match a given market or supplier brief.

Scheduling takes two minutes. No commitment.