List of data centers in the UAE by emirate, operator, and project status

The UAE has 676.5 MW of operating data center IT load, and two emirates account for almost all of it. Abu Dhabi passed Dubai in 2025 and now runs 400.8 MW against Dubai's 263.6 MW. But the 6,151 MW pipeline is nearly nine times today's base, and nearly every new megawatt is being designed for AI-density racks.

Published November 25, 2026

676.5 MW
UAE operating IT load
6,151.3 MW
UAE pipeline IT load
400.8 MW
Abu Dhabi operating IT load
263.6 MW
Dubai operating IT load

Mordor Intelligence, Data Center Intelligence research team. Facility data as of November 2026.

Key takeaways

  • 01Two emirates, 98% of the market.
    Abu Dhabi (59.2%) and Dubai (38.9%) together run 664.4 MW of the UAE's 676.5 MW operating IT load.
  • 02Colocation is the market.
    Colocation buildings carry 644.4 MW, or 95.3% of operating load.
  • 03The cooling switch is in the pipeline.
    72.6% of today's load sits in halls designed for 20 kW per rack or less. In the pipeline, 99.7% of the megawatts are designed for 35 kW per rack or more, the density at which liquid cooling becomes the norm.
  • 04One campus dominates the future.
    The UAE–US AI Campus phases account for 3,935 MW, 64% of the pipeline. Without it and the Asprofin proposal, the named pipeline is a far more modest 515 MW.

UAE data center projects by operating status

Data Center Intelligence (DCI) tracks more than 95 UAE records. The market has grown fast but from a small base. Operating IT load rose from 206 MW at the end of 2020 to 676.5 MW at the end of 2025. If every phase opens on its operator's target date, it reaches 1,338 MW by the end of 2026, almost twice the 2025 figure.
Selected data centers in the UAE
Mordor Intelligence, Data Center Intelligence research team. Facility data as of November 2026.
OperatorData Center FacilityCityIT loadStatus
Equinix Inc.DX1Dubai6.14 MWCommissioned
Khazna Data Centers LLCDXB8Dubai12.46 MWCommissioned
Khazna Data Centers LLCAUH6Abu Dhabi31.8 MWCommissioned
Pure Data Centres Group LimitedAUH01 Building 1Abu Dhabi27 MWCommissioned
UAE operating IT load by year-end
Operating IT load in MW. 2026 and 2028 values assume each phase opens on its target date; targets are not secured power or handover dates.
Year-endAbu DhabiDubaiRest of UAEUAE totalLeader
2020121.878.16.1206.0Abu Dhabi
2022167.9185.99.5363.3Dubai
2024223.8263.59.5496.8Dubai
2025400.8263.612.0676.5Abu Dhabi
2026, if on schedule838.5403.396.21,338.0Abu Dhabi
2028, if on schedule4,503.5496.296.25,095.9Abu Dhabi

In one line: Dubai led for four straight year-ends. A single 150 MW AI building flipped the ranking in 2025.

Khazna is the market's anchor. It runs 24 of the 61 operating buildings and 194.4 MW, 28% of the UAE's live load, and is also the developer behind the AI Campus build. Moro Hub (73 MW), Gulf Data Hub (48.2 MW), du (42.9 MW), e& (33.4 MW), and Equinix (30.7 MW) are the next largest.

Directory sites report different UAE totals because some count campuses and others count individual buildings or halls. DCI counts each building or construction phase once. Where a project has a public headline that differs from its phased record, such as Khazna's 100 MW QAJ1 in Ajman (75.2 MW recorded as the phase under construction), we show both.

Where are data centers located in the UAE?

Abu Dhabi: many zones, one giant AI campus

Abu Dhabi's 400.8 MW is spread across more than seven zones. One building, G42's UAE DC1, is designed at 70 kW per rack and accounts for 150 MW, or 37% of the emirate's live load.
Abu Dhabi data center zones
Abu Dhabi operating and pipeline IT load by zone, checked November 2026.
ZoneOperating (MW)Pipeline (MW)Main operatorsWhat defines it
KEZAD / Khalifa Industrial Zone74.140.0Khazna, du, Gulf Data HubThe emirate's densest cluster: 11 operating buildings, mostly Khazna's AUH5 and AUH7 halls of about 4 MW each
Masdar City49.730.0Khazna, EquinixKhazna AUH6 (31.8 MW) and AUH1, Equinix AD1; Khazna AUH8 is under construction
Zayed Military City36.0–KhaznaSix 6 MW AUH2 halls, all from 2012
Yas Island27.021.0Pure DCPure DC's 48 MW AUH01 campus; Building 2 is next
Khalifa City17.4–Khazna, e&Legacy telco and government sites
Mafraq–52.6KhaznaNew ground: AUH4 (30 MW) and a 22.6 MW Khazna phase
ICAD / Mussafah4.024.0Gulf Data Hub, G42Gulf Data Hub's 12 MW ICAD 3 and 4 buildings
Al Ain8.4–Khazna, e&Small regional sites
Abu Dhabi184.33,982.2G42/Core42, duG42 UAE DC1, and the UAE–US AI Campus

Dubai: three clusters and a solar-powered giant

Dubai runs 263.6 MW across 37 records. It has more operators than Abu Dhabi and a more retail, interconnection-led market, but no single building larger than Moro Hub's Solar Park facility.
Dubai Silicon Oasis is the corridor to watch. Gulf Data Hub has eight phases there (DSO 6 to DSO 13) under construction, each designed for 70 kW per rack, and VOLT Datacenters has announced two phases totalling 98.7 MW.
Watch this corridor: Dubai Silicon Oasis has 200.7 MW in its pipeline, more than any other named zone in Dubai outside the Asprofin proposal.
Dubai data center zones
Dubai operating and pipeline IT load by zone, checked November 2026.
ZoneOperating (MW)Pipeline (MW)Main operatorsWhat defines it
MBR Solar Park66.71,090.9Moro Hub, Asprofin (proposed)Moro Hub's solar-powered Green Data Center, Dubai's largest building
Jebel Ali60.9–Khazna, Moro Hub, Pacific Controls, e&Five operating buildings near the port and free zone
Dubai Silicon Oasis53.2200.7Gulf Data Hub, du, VOLTDubai's growth corridor: 94 MW of Gulf Data Hub phases, du Phase 2, VOLT's 98.7 MW plan
Dubai Production City (IMPZ)27.6–Equinix, datamenaThe interconnection hub: Equinix DX1 and DX3
Meydan / Business Bay and other49.2–Khazna, Equinix, Web WerksKhazna DXB1 and DXB2, Equinix DX2
Dubai Internet City6.0–CtrlS, eHosting DataFortSmall enterprise and managed-hosting suites
Hatta–609.8Asprofin (proposed)Part of a proposal still under feasibility assessment

Beyond the two big emirates

The northern emirates run just 12.1 MW today (Fujairah 7.6 MW, Sharjah 4.5 MW), but this is changing. Khazna's QAJ1 in Ajman is the largest single phase under construction outside the AI Campus. Fujairah's role is connectivity rather than scale: e&'s SmartHub sites sit by the subsea cable landings. In Ras Al Khaimah, Siada launched a sovereign AI cloud facility offering NVIDIA B200 GPU-as-a-Service in July 2026, though its capacity has not been disclosed.

Colocation, cloud and cooling in UAE data centers

Colocation hosts almost everything, including the clouds

DCI classifies 58 of the 61 operating buildings as colocation. That covers wholesale operators (Khazna, Gulf Data Hub, Pure DC), retail and interconnection players (Equinix, datamena), and telco-led operators (du, e&, Moro Hub).
The cloud market is an emerging market and is expected to grow at a faster pace in the coming years. In the UAE, cloud providers lease rather than build. Microsoft runs UAE North in Dubai and UAE Central in Abu Dhabi, and Oracle runs UAE East in Dubai and UAE Central in Abu Dhabi. Google Cloud had no UAE region as of October 2026.
Three cloud stories are driving the news:
  • Microsoft's 200 MW through Khazna. Microsoft and G42 announced a 200 MW expansion, to be delivered by Khazna, expected to come online before the end of 2026, as part of Microsoft's $15.2 billion UAE investment. This is cloud demand being met through colocation, which is why it should not simply be added to Khazna's own project totals.
  • Sovereign cloud. Abu Dhabi's government signed Microsoft and Core42 for a sovereign cloud system in March 2025. In February 2026, the Central Bank of the UAE partnered with Core42 on sovereign financial cloud infrastructure, and du's National Hypercloud runs on Oracle Alloy for Dubai and Northern Emirates public-sector customers.
  • SaaS firms localizing. Zoho opened data centers in Dubai and Abu Dhabi at the start of 2026.

Cooling: from air and adiabatic to direct-to-chip

Rack density is the best proxy DCI holds for cooling design, and it shows a clean break between the installed base and the pipeline.
Today, 491.4 MW (72.6%) runs in halls designed for 20 kW per rack or less, which is air-cooled territory. Only six operating buildings, led by G42's UAE DC1, are designed for 35 kW or more. In the pipeline, every phase under construction is designed for at least 35 kW per rack, and 18 of the 22 are designed for 70 kW. Designed efficiency improves too: the median design PUE is 1.47 for operating buildings, 1.33 for phases under construction and 1.27 for announced projects.
What operators are actually installing:
  • Direct-to-chip liquid cooling. Khazna's QAJ1 AI-optimized data centre in Ajman is a 100 MW overall development, comprising 20 data halls designed at 5 MW each. The project has a recorded 75.2 MW IT load capacity for the phase under construction. In February 2026, QAJ1 received Uptime Institute Tier III Certification of Design Documents, positioning it as the first Tier-certified liquid-cooled AI data centre in MENA. Khazna describes its cooling architecture as air-assisted direct-to-chip liquid cooling. For this analysis, 100 MW is reported as the overall project capacity, while 75.2 MW is reported separately as the IT load capacity. Separately, du's 5.1 MW NVIDIA AI supercluster at Dubai Silicon Oasis uses direct-to-chip liquid cooling to support high-density GPU workloads.
  • Adiabatic and evaporative cooling, still the workhorse. Khazna equipped 19 data centers with adiabatic free cooling in 2025 and still primarily uses air-based cooling, adding liquid for higher-density AI halls.
  • Hybrid air and liquid. Pure DC's AUH01 campus on Yas Island is designed for hybrid air and liquid cooling.
  • Modular liquid-cooled units. INNOVO, Castrol ON and LiquidStack are testing a containerised, direct-to-chip proof-of-concept unit in the UAE.
  • Water is the new constraint. Khazna's facilities used about 393,000 m³ of water in 2025, 305,116 m³ of it for cooling, with 19.8% recycled. DXB1 in Dubai cools with treated sewage effluent.
UAE operating IT load by design rack density
UAE operating buildings and pipeline IT load by designed rack density, checked November 2026.
Design densityOperating buildingsOperating IT load (MW)Pipeline (MW)
Up to 10 kW per rack36302.2–
10–20 kW per rack19189.220
35 kW per rack and above6185.16,131.30

UAE data center projects under construction or announced

The UAE pipeline is 6,151 MW, but it is very concentrated. Here are the largest projects.
Stargate UAE sets the pace. The first 200 MW of the 1 GW Stargate UAE cluster, developed by Khazna with OpenAI, Oracle, NVIDIA, Cisco and SoftBank, was due for completion in Q4 2026. ALEC reports building structures erected and MEP works well underway. The rest of the 1 GW cluster and the wider 5 GW campus have no confirmed completion timelines, and Reuters reports that the 5 GW plan may become a network of sites across the UAE rather than one Abu Dhabi campus. Note that DCI records Phase 1 at 375.9 MW, larger than the public 200 MW first tranche.
Largest UAE data center projects under construction or announced
The largest UAE data center projects under construction or announced, ranked by IT load, checked November 2026.
ProjectOperatorWhereStatusIT load (MW)TargetRack design (kW)
UAE–US AI Campus, Phase 3G42 / Core42 (Khazna)Abu DhabiUnder construction3,174.6202850
Sovereign AI data center programmeAsprofinDubai (Solar Park, Hatta)Announced, feasibilityup to 1,700.72029–203160–100
UAE–US AI Campus, Phase 2G42 / Core42 (Khazna)Abu DhabiUnder construction384.6202740
UAE–US AI Campus, Phase 1G42 / Core42 (Khazna)Abu DhabiUnder construction375.9Q4 202635
Dubai DC2, Phase 2VOLT DatacentersDubai Silicon OasisAnnounced76.9202840
QAJ1KhaznaAjmanUnder construction75.2 (100 MW design)Q4 202670
EITC Abu Dhabi DC1duAbu DhabiAnnounced47.0203175
AUH4KhaznaMafraqUnder construction30.0Q4 202670
AUH8KhaznaMasdar CityUnder construction30.0Q4 202670
UAE DC2KhaznaMafraqUnder construction22.6Q4 202670
Dubai DC1, Phase 1VOLT DatacentersDubai Silicon OasisAnnounced21.8Q4 202635
AUH01 Building 2Pure DCYas IslandUnder construction21.0Q4 202635

The end of 2026 is crowded. Nineteen phases worth 661.5 MW carry a 2026 target. Beyond the AI Campus, these include QAJ1, AUH4 and AUH8, Khazna's Mafraq phase, Pure DC's Building 2, VOLT's first Dubai phase and eight Gulf Data Hub phases at Dubai Silicon Oasis. Khazna's QAJ1 is due in December 2026.

Without the mega-projects, growth is steadier. Excluding the AI Campus and Asprofin, UAE operating load would reach about 1,161 MW by 2028, about 484 MW more than today. That is the figure to plan against if the AI Campus phases slip or are re-sited.

Dubai's next wave is still on paper. Dubai's largest future megawatts are the Asprofin proposal, which is under feasibility assessment for 750–1,280 MW across three campuses (DCI records up to 1,700.7 MW, which we treat as a maximum), and du's planned 1 GW AI Park. Until these advance, Dubai Silicon Oasis carries Dubai's under-construction growth.

Who is building. DCI records Laing O'Rourke and BK Gulf as contractor participants on Khazna QAJ1 in Ajman, although Laing O'Rourke's appointment as main contractor is independently reported in the project record. It also identifies both firms on Khazna AUH4 in Mafraq and the Mafraq development phase. For Khazna AUH8 in Masdar City, James L. Williams Middle East (JLW), in partnership with McLaren Construction, is the EPC main contractor; BK Gulf is also identified by DCI, but its specific contractual role requires independent confirmation. For Pure DC's Abu Dhabi campus – Building 2, Laing O'Rourke is the construction partner, although the cited announcement confirms the first data hall and subsequent campus development rather than a specific Building 2 appointment. From a DCI perspective, phases scheduled for completion in Q4 2026 are likely to have progressed beyond their main equipment-award stage. In contrast, the 2027–2028 AI Campus phases, VOLT's Dubai AI data-centre phases and du's Abu Dhabi DC1 are at earlier stages of their development lifecycle. DCI does not track available data-centre space or tender status.

Questions about data centers in the UAE

  • 01

    How many data centers are in the UAE?

    DCI tracks more than 95 data center records in the UAE, 90 with quantified capacity, from 18 operators: 61 operating buildings, 22 phases under construction, six announced projects and one commissioned building with no live load yet. They hold 676.5 MW of operating IT load and 6,151.3 MW in the pipeline.

  • 02

    Which is bigger, Abu Dhabi or Dubai?

    Abu Dhabi, with 400.8 MW of operating IT load against 263.6 MW in Dubai. Abu Dhabi also holds most of the pipeline, through the UAE–US AI Campus.

  • 03

    Who is the largest data center operator in the UAE?

    Khazna Data Centers, with 24 operating buildings and 194.4 MW, 28% of the UAE's operating IT load. It is also building QAJ1, AUH4, AUH8 and the Stargate UAE phases.

  • 04

    Which cloud providers have UAE regions?

    Microsoft (UAE North, Dubai; UAE Central, Abu Dhabi), Oracle (UAE East, Dubai; UAE Central, Abu Dhabi) and AWS (Middle East (UAE) region). Google Cloud had no UAE region as of October 2026.

  • 05

    Are UAE data centers moving to liquid cooling?

    In the pipeline, yes. Every phase under construction is designed for at least 35 kW per rack, and most for 70 kW. Khazna's QAJ1 in Ajman is designed for liquid cooling, and du uses direct-to-chip cooling at its Dubai Silicon Oasis AI cluster. Most operating halls are still air-cooled, often with adiabatic or evaporative assistance.

  • 06

    What is Stargate UAE?

    A 1 GW AI compute cluster in Abu Dhabi, being developed by Khazna with OpenAI, Oracle, NVIDIA, Cisco and SoftBank, inside the planned 5 GW UAE–US AI Campus. Its first 200 MW was targeted for 2026.

  • 07

    Does Data Center Intelligence offer a free trial?

    Yes. The DCI team starts with a 30-minute walkthrough tailored to your market, then opens a trial for your team.

Explore the UAE projects in Data Center Intelligence

For a new development, use the DCI site selection tool to compare candidate locations against your project requirements. Data Center Intelligence holds the full UAE list, with filters for emirate, zone, operator, status, capacity band, rack density, PUE, Tier level and target date, plus construction stakeholders and IT load by year from 2016 to 2036. A demonstration walks through the facilities and phases that match your market or supplier brief.