List of data centers in South Africa by city, operator and project status

South Africa runs 528.04 MW of tracked data center IT load today, and Data Center Intelligence tracks 668.18 MW of expected IT load under construction, announced or planned. This page sizes the market, maps the hotspots, sets out who runs colocation and cloud capacity and how operators cool it, and lists the projects that arrive next.

Published November 25, 2026

78
Records tracked
528.04 MW
Operating IT load
668.18 MW
Expected IT load
63
Checked live buildings

Mordor Intelligence, Data Center Intelligence research team. DCI South Africa records, November 2026.

Selected South Africa data center records
Selected South Africa data center records, checked November 2026.
Data Center OperatorData Center FacilityCityStatusOperational IT load Capacity
Digital Parks Africa (PTY) LTD.ZA - Samrand DatacentreGautengCommissioned18 MW
NTT DATA GROUP CorporationBryanston Data CenterGautengCommissioned1.33 MW
Africa Data CentresCPT1, Cape Town Data CentreCape TownCommissioned9 MW
Teraco Data EnvironmentsJB1 (East & West)GautengCommissioned35 MW
Amazon Web Services, Inc.Amazon AWS CPT - AtlanticCape TownCommissioned50 MW
Teraco Data EnvironmentsJB7GautengUnder Construction30.08 MW (expected Q4 2026)

How many operating data center buildings are in South Africa?

DCI distinguishes 68 operating records from 63 checked live buildings. A record can describe a phase or part of a building.
Gauteng carries the market. The Johannesburg–Pretoria corridor runs 375.6 MW, 71% of operating IT load. Cape Town holds 139.0 MW (26%).
Colocation dominates. DCI classifies 74 of 78 records as colocation, and Teraco alone runs 21% of operating load. AWS and Microsoft hold the only two cloud provider sites.
One large phase is under construction. Teraco JB7 (30.1 MW, Q4 2026) is the only phase of 20 MW or more under construction. Microsoft’s Centurion site (50.0 MW, 2028) is recorded as announced, and Cosmas Data Cities holds 91% of announced load.
South African data center records by status
South African data center records by status, checked November 2026.
StatusRecordsIT load (MW)
Operating68528.04
Under Construction452.88
Announced4615.30
Planned2–
Total781,196.22

Major hotspots: Gauteng leads, Cape Town follows

Gauteng holds 44 records and 375.6 MW of operating load, with Johannesburg alone at 282.7 MW. Cape Town, including Bellville, holds 23 records and 139.0 MW. Together the two regions run 97% of South Africa’s operating IT load.
Data center records by city and status
Data center records by city and status. On the map, circle size shows operating IT load (MW); DCI data as of November 2026. Operating MW values are rounded; they sum to 528.1 against the 528.04 MW (528.0) national total.
South Africa data center records by city and status, checked November 2026.
CityRecordsChecked liveUnder constructionAnnouncedPlannedOperating MW
Gauteng (all)4434430375.6
Johannesburg3224320282.7
Centurion6411054.9
Midrand220002.0
Ekurhuleni1100019.0
Kempton Park1100013.0
Samrand110003.0
Sandton110001.0
Cape Town (incl. Bellville)2320011139.0
Durban (incl. Umhlanga)9700110.7
Bloemfontein110001.5
Gqeberha110001.3
Total7863442528.0

Outside Gauteng and Cape Town, the list thins out. Durban has 9 records but only 10.7 MW running, and its largest prospect is a planned campus with no operator recorded. Cape Town has 1 announced record, Cosmas Data Cities Cape Town DC1, at 360.0 MW, matching the one Cape Town campus Cavaleros has announced. Its planned record is an Equinix site with no recorded capacity.

Largest operating data centers in Gauteng

Gauteng holds 37 operating records, and Equinix JN1 Phase 2 (5.3 MW) is under construction in Johannesburg for 2027. Teraco’s JB1 and JB3 and ADC’s JHB2 Samrand site lead, each recorded at 35 MW. Most operators run one or two halls in Gauteng and a smaller presence in Cape Town and Durban.
The nine largest operating data centers in Gauteng
The nine largest operating data centers in Gauteng, ranked by IT load.
The nine largest operating data centers in Gauteng, ranked by IT load, checked November 2026.
FacilityOperatorCityIT load (MW)Tier type recordedkW/rackPower redundancyOpened
ADC JHB2 SamrandAfrica Data CentreCenturion35.0Tier 47N+12018
Teraco JB3TeracoJohannesburg35.0Tier 37.5N+12021
Teraco JB1 (East and West)TeracoJohannesburg35.0Tier 34N+12010
Teraco JB5TeracoJohannesburg22.1Tier 3142N2025
Vantage JNB2VantageJohannesburg20.0Tier 414N+12025
Teraco JB4TeracoEkurhuleni19.0Tier 3202N2022
Digital Parks Africa ZA-SamrandDigital Parks AfricaCenturion18.0Tier 342N2017
Vantage JNB1, building 2VantageJohannesburg16.0Tier 46N+12024
Vantage JNB1, building 1VantageJohannesburg16.0Tier 46N+12022

Colocation, cloud and cooling in South Africa

Colocation operators run the market

DCI classifies 74 records as colocation, 2 as cloud provider sites (AWS, operating in Cape Town, and Microsoft, announced in Centurion), and one as enterprise (Visa). Teraco leads by operating load, with 111.1 MW across 10 operating records in Gauteng, Cape Town and Durban, 21% of the national total. Africa Data Centres, Vantage, AWS and BCX follow. Cavaleros Group, the developer behind Cosmas Data Cities, holds the largest announced pipeline but no operating site.
The ten largest operators
The ten largest operators by total operating and pipeline IT load (MW).
The ten largest South African operators by total operating and pipeline IT load, checked November 2026.
OperatorRecordsAreasOperatingPipelineTotal
Cavaleros (Cosmas Data Cities)2Cape Town, Gauteng0.0560.0560.0
Teraco11Cape Town, Durban, Gauteng111.130.1141.2
Africa Data Centres6Cape Town, Gauteng103.05.0108.0
Vantage4Gauteng52.016.068.0
AWS1Cape Town50.00.050.0
Microsoft1Gauteng0.050.050.0
BCX4Durban, Gauteng24.10.024.1
NTT DATA9Bloemfontein, Cape Town, Durban, Gauteng, Gqeberha22.80.022.8
Digital Parks Africa2Gauteng21.00.021.0
Open Access Data Centres4Cape Town, Durban, Gauteng15.30.015.3

Cloud providers: one operating, one announced

AWS runs 50.0 MW in Cape Town (Atlantic) at 12 kW per rack. Microsoft’s 50.0 MW Centurion site, targeted for 2028, is recorded as announced rather than under construction. The 50 MW figure is a DCI estimate, and the site would serve Microsoft’s own cloud operations rather than third-party colocation supply.

Which Gauteng facilities meet the buyer’s rack density and cooling technology needs?

Operators of the denser halls cool them mainly with chilled water. Teraco runs chilled water with free-air cooling at JB5 and CT2 Phase 2, and enables liquid-to-liquid cooling at JB4. Vantage runs chilled water with air-cooled chillers and an economizer at JNB2. ADC runs hot-aisle/cold-aisle containment at JHB1 Midrand, and DPA runs dual-circuit cooling at Samrand.
Sites recording 12 kW per rack or more
Operating and under-construction sites recording 12 kW per rack or more, tested against the brief.
Operating and under-construction South African sites recording 12 kW per rack or more, checked November 2026.
FacilityCitykW/rackPower redundancyCooling redundancyCooling method
Teraco JB4Ekurhuleni202NN+1Chilled water, free-air cooling; liquid-to-liquid cooling enabled
ADC CPT2 (expansion)Cape Town182NN+1–
Equinix JN1 Phase 2 (under construction, 2027)Johannesburg16.5N+1N+2–
ADC JHB1 Midrand Phase 1Johannesburg15.2N+1N+1Hot-aisle/cold-aisle containment
ADC JHB1 Midrand (probable duplicate record)Johannesburg15N+1N+1Hot-aisle/cold-aisle containment
Visa South Africa DC1Johannesburg152NN+1–
Teraco JB5Johannesburg142NN+1Chilled water with free-air cooling
Teraco CT2 Phase 2Cape Town14N+1N+1Chilled water with free-air cooling
Vantage JNB2Johannesburg14N+1N+2Chilled water with air-cooled chillers and economizer
DPA SamrandSamrand14N+1N+1Dual-circuit cooling
AWS Cape Town (Atlantic)Cape Town12N+1N+1–

One site passes. Teraco JB4 in Ekurhuleni is the only operating colocation facility in Gauteng that meets all three requirements on DCI-recorded values. Those three values are DCI estimates: Teraco’s published material confirms a 30 MW Phase 2 of six 5 MW halls with liquid-to-liquid cooling, but does not publish rack density or redundancy for the phase. ADC CPT2 in Cape Town meets the density and redundancy criteria but fails on geography, and DCI records UPS-only backup power for it. Teraco JB5 and Vantage JNB2 fall just below the density threshold at 14 kW, while ADC JHB1 Midrand meets the density requirement but records only N+1 power. Equinix JN1 Phase 2 (16.5 kW) is still under construction and records N+1 power. Visa South Africa DC1 meets the technical criteria but fails as an enterprise facility rather than a colocation option; its capacity, density and redundancy values are DCI estimates, as Visa has not published them.

Resilience and efficiency

DCI records the fields that compare across sites: management system certifications, backup power and efficiency.
Certifications recorded across South African records
Certifications recorded across South African records.
Certifications recorded across South African data center records, checked November 2026.
Certification recordedRecords
ISO 27001 (information security)75
PCI DSS (payment card security)54
ISO 50001 (energy management)32
ISAE 3402 or similar assurance report27
ISO 14001 (environment)25
ISO 22301 (business continuity)21
SOC 1 or SOC 2 report8
TIA-942 Rated-3 (operator-stated)5

Backup power. 74 records list generators plus UPS. Three list UPS only: ADC CPT2 (expansion), Xneelo Samrand DC1 and Xneelo Samrand DC2. Buyers should ask each operator for generator autonomy in hours and fuel contract terms, which DCI does not record.

Efficiency. Of the 68 operating records, 28 carry a site-specific PUE, ranging from 1.36 to 1.58 with a median of 1.44. Equinix JN1 Phase 2, under construction, records a design PUE of 1.30, which is not included. The remaining 40 operating records use a DCI estimate of 1.55 for older or smaller sites. These estimates are excluded from the range and median and have not been independently verified. Buyers should compare facilities on measured PUE, allowing for differences in measurement periods and operating conditions.

Future developments: phased builds and the calendar

The next additions

Teraco JB7 leads the next wave, with commissioning expected in Q4 2026 and DCI-recorded specifications of 15 kW per rack and 2N power. Vantage JNB1 Building 3, due in 2027, adds further high-density capacity; Microsoft’s Centurion development, announced but not yet under construction, is targeted for 2028. DCI records Abbeydale Construction, B2 Architects and EDS Engineers on Teraco JB7, and CKR Consulting Engineers, WBHO Construction and Turner & Townsend on Vantage JNB1 Building 3. Microsoft’s Centurion site names no contractors.

Phased and modular builds raise density

Operators increasingly deliver South African capacity in phases and as prefabricated modules rather than as single large buildings, and each phase can move density sharply.
Phase-by-phase records at three campuses
Phase-by-phase records at three campuses.
Phase-by-phase records at three South African campuses, checked November 2026.
CampusPhase or buildingStatusIT load (MW)YearTier type recordedkW/rackPower/cooling redundancy
Equinix JN1Equinix JN1 Phase 1Operating2.72024Tier 46N+1 / N+1
Equinix JN1Equinix JN1 Phase 2Under Construction5.32027Tier 416.5N+1 / N+2
Equinix JN1Equinix JN1 Phase 3Announced5.32028Tier 417N+1 / N+1
Vantage JNB1Vantage JNB1, building 1Operating16.02022Tier 46N+1 / N+1
Vantage JNB1Vantage JNB1, building 2Operating16.02024Tier 46N+1 / N+1
Vantage JNB1Vantage JNB1, building 3Under Construction16.02027Tier 470N+1 / N+2
xneelo Samrandxneelo Samrand DC1Operating0.92013Tier 332N / N+1
xneelo Samrandxneelo Samrand DC2Under Construction1.52026Tier 3702N / N+1

Density changes phase by phase. Vantage’s first two JNB1 buildings record 6 kW per rack; the third records 70 kW. Xneelo’s Samrand DC1 records 3 kW; DC2 records 70 kW. Equinix JN1 rises from 6 kW in Phase 1 to 16.5–17 kW in Phases 2 and 3. A campus-level figure hides all of this.

When new capacity arrives

IT load due by year (MW). All years shown, Q4 2026 to 2028, are forecasts; Cosmas Data Cities load is identified separately. *Cosmas JHB DC1 carries a 2027 target in its record; the DCI yearly capacity series places it in 2028.
Expected IT load by target year
Expected South African IT load by target year, checked November 2026.
YearUnder construction, due (MW)Announced or planned, target (MW)
2026 (Q4, forecast)31.6 + 5.0 ADC CPT2 expansion–
2027 (forecast)21.3 (Vantage JNB1 building 3 16.0 + Equinix JN1 Phase 2 5.3)–
2028 (forecast)–615.3 (Cosmas CPT DC1 360.0, Cosmas JHB DC1 200.0*, Microsoft 50.0, Equinix JN1 Phase 3 5.3)

Two things to watch

  • Q4 2026 handovers.
    Teraco JB7 and Xneelo Samrand DC2 both fall due in the fourth quarter of 2026. Their handover sets Gauteng’s high-density supply for 2027.
  • Cosmas Data Cities.
    The two Cosmas Data Cities records hold 560.0 MW, 91% of announced load, and match the two campuses Cavaleros has announced: Johannesburg (Samrand, 200 MW) and Cape Town (360 MW). The DC2 records that raised a duplication question are no longer in the datasheet, so expected IT load is 668.18 MW. A construction start at either campus will change South Africa’s pipeline more than any other event.

Questions about data centers in South Africa

  • 01

    How many data centers are in South Africa?

    DCI tracks 78 data center records in South Africa: 68 operating (528.04 MW), 4 under construction (52.88 MW), 4 announced (615.3 MW), and 2 planned (no IT load disclosed).

    Which South African city has the most data centers? Johannesburg, within Gauteng. Gauteng holds 44 records and 375.6 MW of operating IT load; Cape Town holds 23 records and 139.0 MW.

  • 02

    Who is the largest data center operator in South Africa?

    Teraco, with 111.1 MW of operating IT load across 10 operating records in Gauteng, Cape Town and Durban.

  • 03

    Which data centers in Johannesburg support high-density racks?

    Among operating sites, Teraco JB4 phase 2 records 20 kW per rack, ADC JHB1 Midrand Phase 1 15.2 kW, and Teraco JB5 and Vantage JNB2 14 kW. Vantage’s third JNB1 building, due in 2027, records 70 kW.

  • 04

    Which cooling technologies do South African data centers use?

    Chilled water dominates the denser halls, often paired with free-air cooling or economizers. Teraco enables liquid-to-liquid cooling at JB4.

  • 05

    Who is building South Africa’s new data centers?

    DCI records Abbeydale Construction, B2 Architects and EDS Engineers on Teraco JB7, and CKR Consulting Engineers, WBHO Construction and Turner & Townsend on Vantage JNB1’s third building. Microsoft’s Centurion site names no contractors.

  • 06

    Does Data Center Intelligence offer a free trial?

    Yes. The DCI team starts with a 30-minute walkthrough tailored to your market, then opens a trial for your team.

Explore the South African projects in DCI.

DCI holds the full South African list with filters for city, operator, status, capacity, rack density, redundancy, tier type, and expected year. A demonstration walks through the facilities and projects that match your brief. For a new development, use the DCI site selection tool to compare candidate locations against your project requirements.

Scheduling takes two minutes. No commitment.